5-Blade 9-Meter Ni-Al-Bronze Ship Propeller

Product family: Fixed-Pitch Ocean Propellers.

Flow: Cu3 Nickel-Aluminum Bronze → Cement-Sand Pit Mold Pour → 5-Axis Giant Blade Pitch Mill → Dye-Penetrant Tip & Fillet → Hand Hydrodynamic Mirror Buff → Static Knife-Edge Balance QC → Commercial Shipbuilders

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 5-Blade 9-Meter Ni-Al-Bronze Ship PropellerSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Cu3 Nickel-Aluminum Bronze → Cement-Sand Pit Mold Pour (11,880 s) → 5-Axis Giant Blade Pitch Mill (14,400 s) → Dye-Penetrant Tip & Fillet (19,440 s) → Hand Hydrodynamic Mirror Buff (14,040 s) → Static Knife-Edge Balance QC (11,160 s) → Commercial Shipbuilders.SUPPLIERCu3Nickel-AluminumBronzeI2.00 d1Cement-Sand PitMold PourC/T 11,880 sI1.67 d25-Axis GiantBlade Pitch MillC/T 14,400 sI2.67 d3Dye-Penetrant Tip& FilletC/T 19,440 sI1.33 d4Hand HydrodynamicMirror BuffC/T 14,040 sI1.00 d5Static Knife-EdgeBalance QCC/T 11,160 sI1.67 dCUSTOMERCommercialShipbuilders3 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Cement-Sand Pit Mold Pour11,880 s30 min95%99.0%56 (2.00 d)4
2. 5-Axis Giant Blade Pitch Mill14,400 s35 min92%97.6%35 (1.67 d)3
3. Dye-Penetrant Tip & Fillet19,440 s45 min84%95.4%38 (2.67 d)2
4. Hand Hydrodynamic Mirror Buff14,040 s25 min92%97.8%24 (1.33 d)3
5. Static Knife-Edge Balance QC11,160 s15 min95%98.9%23 (1.00 d)4

Key figures

Takt time
18,000 s
Lead time
11.6 d
Value-added time
70,920 s
Process cycle efficiency (PCE)
11.3%
Rolled throughput yield (RTY)
89.2%
Customer demand per day
3 parts
Line capacity per day
2 parts
Bottleneck
Dye-Penetrant Tip & Fillet

Reading the bottleneck

The bottleneck is "Dye-Penetrant Tip & Fillet": it can process 2 parts per day against a demand of 3 parts, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 19,440 s to 24,259 s, against a takt of 18,000 s. The largest loss at this step is equipment downtime (uptime 84%), about 3,703 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.