11-Meter XXL Offshore Wind Monopile Rolling Line
Product family: 2,400T Ocean Pile Foundations.
Flow: Heavy Steel Plate Mills → Bevel Milling & 3-Roll Bending → Tandem Longitudinal SAW Weld → Ring-to-Ring Circumferential → 100% Automated Phased-Array → Flange Grind & Quay Rollout → Offshore Wind Installation
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Bevel Milling & 3-Roll Bending | 26,730 s | 30 min | 95% | 99.0% | 3 | 4 (2.00 d) | 3 |
| 2. Tandem Longitudinal SAW Weld | 32,400 s | 35 min | 92% | 97.6% | 2 | 4 (2.00 d) | 2 |
| 3. Ring-to-Ring Circumferential | 43,740 s | 45 min | 84% | 95.4% | 2 | 5 (2.50 d) | 1 |
| 4. 100% Automated Phased-Array | 31,590 s | 25 min | 92% | 97.8% | 2 | 3 (1.50 d) | 2 |
| 5. Flange Grind & Quay Rollout | 25,110 s | 15 min | 95% | 98.9% | 1 | 2 (1.00 d) | 3 |
Key figures
- Takt time
- 40,500 s
- Lead time
- 12.5 d
- Value-added time
- 159,570 s
- Process cycle efficiency (PCE)
- 15.8%
- Rolled throughput yield (RTY)
- 89.2%
- Customer demand per day
- 2 units
- Line capacity per day
- 1 units
- Bottleneck
- Ring-to-Ring Circumferential
Reading the bottleneck
The bottleneck is "Ring-to-Ring Circumferential": it can process 1 units per day against a demand of 2 units, so it falls short of demand by 28.3%. Once downtime and scrap are counted, its cycle time grows from 43,740 s to 54,582 s, against a takt of 40,500 s. The largest loss at this step is equipment downtime (uptime 84%), about 8,331 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Shipbuilding, Rail Rolling Stock & Heavy: Shipbuilding, Rail Rolling Stock & Heavy
- LNG Carrier Double-Hull Steel Block Assembly
- Offshore Wind 4-Legged Steel Jacket Foundation
- Intermodal 90ft Articulated Rail Container Wagon
- 75m Superyacht Custom Interior Outfitting Bay
- ASME Sec-VIII Petrochemical Hydrocracker Reactor
- Container Vessel Drydock Hull Silane Coating Flow
- 5-Blade 9-Meter Ni-Al-Bronze Ship Propeller
- Inland River Double-Hull Hopper Cargo Barge
- 500-Ton Canal Lock Mitre Gate Overhaul Yard
- 1,200-Ton Shipyard Goliath Bridge Crane Erection
- Cutter-Suction Harbor Dredger Cutterhead Rebuild