1,200-Ton Shipyard Goliath Bridge Crane Erection

Product family: 160m Span Maritime Crane.

Flow: Heavy Box Girder Fabricators → Pier & Pier-Leg Box Welding → Twin-Girder Ground Span Join → Heavy Strand-Jack Hoist Lift → Trolley Rail & 12-Drive Wire → Overload Barge Pull Sign-Off → Global Mega-Shipyards

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 1,200-Ton Shipyard Goliath Bridge Crane ErectionSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Heavy Box Girder Fabricators → Pier & Pier-Leg Box Welding (17,820 s) → Twin-Girder Ground Span Join (21,600 s) → Heavy Strand-Jack Hoist Lift (29,160 s) → Trolley Rail & 12-Drive Wire (21,060 s) → Overload Barge Pull Sign-Off (16,740 s) → Global Mega-Shipyards.SUPPLIERHeavy BoxGirderFabricatorsI2.00 d1Pier & Pier-LegBox WeldingC/T 17,820 sI2.00 d2Twin-GirderGround Span JoinC/T 21,600 sI3.00 d3Heavy Strand-JackHoist LiftC/T 29,160 sI1.00 d4Trolley Rail &12-Drive WireC/T 21,060 sI1.00 d5Overload BargePull Sign-OffC/T 16,740 sI2.00 dCUSTOMERGlobalMega-Shipyards1 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Pier & Pier-Leg Box Welding17,820 s30 min95%99.0%22 (2.00 d)1
2. Twin-Girder Ground Span Join21,600 s35 min92%97.6%12 (2.00 d)1
3. Heavy Strand-Jack Hoist Lift29,160 s45 min84%95.4%13 (3.00 d)1
4. Trolley Rail & 12-Drive Wire21,060 s25 min92%97.8%11 (1.00 d)1
5. Overload Barge Pull Sign-Off16,740 s15 min95%98.9%11 (1.00 d)1

Key figures

Takt time
27,000 s
Lead time
14.9 d
Value-added time
106,380 s
Process cycle efficiency (PCE)
26.4%
Rolled throughput yield (RTY)
89.2%
Customer demand per day
1 units
Line capacity per day
1 units
Bottleneck
Heavy Strand-Jack Hoist Lift

Reading the bottleneck

The bottleneck is "Heavy Strand-Jack Hoist Lift": it can process 1 units per day against a demand of 1 units, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 29,160 s to 36,388 s, against a takt of 27,000 s. The largest loss at this step is equipment downtime (uptime 84%), about 5,554 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.