ASME Sec-VIII Petrochemical Hydrocracker Reactor
Product family: Thick-Wall CrMoV Vessels.
Flow: Forged CrMo Rings → 304SS Internal Weld Overlay → Narrow-Gap Sub-Arc Seam Weld → 100% Linear-Accel Radiograph → Full Furnace PWHT & Hydrotest → Barge Heavy-Haul Saddle Ship → Refinery & Ammonia Plants
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 304SS Internal Weld Overlay | 17,820 s | 30 min | 95% | 99.0% | 3 | 4 (2.00 d) | 3 |
| 2. Narrow-Gap Sub-Arc Seam Weld | 21,600 s | 35 min | 92% | 97.6% | 2 | 4 (2.00 d) | 2 |
| 3. 100% Linear-Accel Radiograph | 29,160 s | 45 min | 84% | 95.4% | 2 | 5 (2.50 d) | 1 |
| 4. Full Furnace PWHT & Hydrotest | 21,060 s | 25 min | 92% | 97.8% | 2 | 3 (1.50 d) | 2 |
| 5. Barge Heavy-Haul Saddle Ship | 16,740 s | 15 min | 95% | 98.9% | 1 | 2 (1.00 d) | 3 |
Key figures
- Takt time
- 27,000 s
- Lead time
- 12.5 d
- Value-added time
- 106,380 s
- Process cycle efficiency (PCE)
- 15.8%
- Rolled throughput yield (RTY)
- 89.2%
- Customer demand per day
- 2 units
- Line capacity per day
- 1 units
- Bottleneck
- 100% Linear-Accel Radiograph
Reading the bottleneck
The bottleneck is "100% Linear-Accel Radiograph": it can process 1 units per day against a demand of 2 units, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 29,160 s to 36,388 s, against a takt of 27,000 s. The largest loss at this step is equipment downtime (uptime 84%), about 5,554 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Shipbuilding, Rail Rolling Stock & Heavy: Shipbuilding, Rail Rolling Stock & Heavy
- LNG Carrier Double-Hull Steel Block Assembly
- Offshore Wind 4-Legged Steel Jacket Foundation
- 11-Meter XXL Offshore Wind Monopile Rolling Line
- Intermodal 90ft Articulated Rail Container Wagon
- 75m Superyacht Custom Interior Outfitting Bay
- Container Vessel Drydock Hull Silane Coating Flow
- 5-Blade 9-Meter Ni-Al-Bronze Ship Propeller
- Inland River Double-Hull Hopper Cargo Barge
- 500-Ton Canal Lock Mitre Gate Overhaul Yard
- 1,200-Ton Shipyard Goliath Bridge Crane Erection
- Cutter-Suction Harbor Dredger Cutterhead Rebuild