LNG Carrier Double-Hull Steel Block Assembly
Product family: 400-Ton Pre-Outfitted Mega-Blocks.
Flow: Marine Grade Plate (AH36) → CNC Plasma Cut & Panel Weld → Curved Egg-Box Frame Fit → Pipe Spool & Cable Pre-Outfit → SA2.5 Blast & Epoxy Coat Cell → 400T SPMT Transfer to Dock → Drydock Goliath Crane
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. CNC Plasma Cut & Panel Weld | 11,880 s | 30 min | 95% | 99.0% | 5 | 6 (2.00 d) | 4 |
| 2. Curved Egg-Box Frame Fit | 14,400 s | 35 min | 92% | 97.6% | 3 | 5 (1.67 d) | 3 |
| 3. Pipe Spool & Cable Pre-Outfit | 19,440 s | 45 min | 84% | 95.4% | 3 | 8 (2.67 d) | 2 |
| 4. SA2.5 Blast & Epoxy Coat Cell | 14,040 s | 25 min | 92% | 97.8% | 2 | 4 (1.33 d) | 3 |
| 5. 400T SPMT Transfer to Dock | 11,160 s | 15 min | 95% | 98.9% | 2 | 3 (1.00 d) | 4 |
Key figures
- Takt time
- 18,000 s
- Lead time
- 11.6 d
- Value-added time
- 70,920 s
- Process cycle efficiency (PCE)
- 11.3%
- Rolled throughput yield (RTY)
- 89.2%
- Customer demand per day
- 3 assemblies
- Line capacity per day
- 2 assemblies
- Bottleneck
- Pipe Spool & Cable Pre-Outfit
Reading the bottleneck
The bottleneck is "Pipe Spool & Cable Pre-Outfit": it can process 2 assemblies per day against a demand of 3 assemblies, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 19,440 s to 24,259 s, against a takt of 18,000 s. The largest loss at this step is equipment downtime (uptime 84%), about 3,703 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Shipbuilding, Rail Rolling Stock & Heavy: Shipbuilding, Rail Rolling Stock & Heavy
- Offshore Wind 4-Legged Steel Jacket Foundation
- 11-Meter XXL Offshore Wind Monopile Rolling Line
- Intermodal 90ft Articulated Rail Container Wagon
- 75m Superyacht Custom Interior Outfitting Bay
- ASME Sec-VIII Petrochemical Hydrocracker Reactor
- Container Vessel Drydock Hull Silane Coating Flow
- 5-Blade 9-Meter Ni-Al-Bronze Ship Propeller
- Inland River Double-Hull Hopper Cargo Barge
- 500-Ton Canal Lock Mitre Gate Overhaul Yard
- 1,200-Ton Shipyard Goliath Bridge Crane Erection
- Cutter-Suction Harbor Dredger Cutterhead Rebuild