LNG Carrier Double-Hull Steel Block Assembly

Product family: 400-Ton Pre-Outfitted Mega-Blocks.

Flow: Marine Grade Plate (AH36) → CNC Plasma Cut & Panel Weld → Curved Egg-Box Frame Fit → Pipe Spool & Cable Pre-Outfit → SA2.5 Blast & Epoxy Coat Cell → 400T SPMT Transfer to Dock → Drydock Goliath Crane

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: LNG Carrier Double-Hull Steel Block AssemblySupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Marine Grade Plate (AH36) → CNC Plasma Cut & Panel Weld (11,880 s) → Curved Egg-Box Frame Fit (14,400 s) → Pipe Spool & Cable Pre-Outfit (19,440 s) → SA2.5 Blast & Epoxy Coat Cell (14,040 s) → 400T SPMT Transfer to Dock (11,160 s) → Drydock Goliath Crane.SUPPLIERMarine GradePlate (AH36)I2.00 d1CNC Plasma Cut &Panel WeldC/T 11,880 sI1.67 d2Curved Egg-BoxFrame FitC/T 14,400 sI2.67 d3Pipe Spool &Cable Pre-OutfitC/T 19,440 sI1.33 d4SA2.5 Blast &Epoxy Coat CellC/T 14,040 sI1.00 d5400T SPMTTransfer to DockC/T 11,160 sI1.67 dCUSTOMERDrydock GoliathCrane3 / assemblies

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. CNC Plasma Cut & Panel Weld11,880 s30 min95%99.0%56 (2.00 d)4
2. Curved Egg-Box Frame Fit14,400 s35 min92%97.6%35 (1.67 d)3
3. Pipe Spool & Cable Pre-Outfit19,440 s45 min84%95.4%38 (2.67 d)2
4. SA2.5 Blast & Epoxy Coat Cell14,040 s25 min92%97.8%24 (1.33 d)3
5. 400T SPMT Transfer to Dock11,160 s15 min95%98.9%23 (1.00 d)4

Key figures

Takt time
18,000 s
Lead time
11.6 d
Value-added time
70,920 s
Process cycle efficiency (PCE)
11.3%
Rolled throughput yield (RTY)
89.2%
Customer demand per day
3 assemblies
Line capacity per day
2 assemblies
Bottleneck
Pipe Spool & Cable Pre-Outfit

Reading the bottleneck

The bottleneck is "Pipe Spool & Cable Pre-Outfit": it can process 2 assemblies per day against a demand of 3 assemblies, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 19,440 s to 24,259 s, against a takt of 18,000 s. The largest loss at this step is equipment downtime (uptime 84%), about 3,703 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.