Inland River Double-Hull Hopper Cargo Barge
Product family: Automated Box-Barge Line.
Flow: Shot-Blasted Steel Coils → Batch Laser Nesting Bulkheads → Automated Fillet Weld Gantry → Sectional Weld & Vacuum Test → Hatch Covers & Winch Mount → Slipway Launch & Class Approval → Rhine & Mississippi Fleets
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Batch Laser Nesting Bulkheads | 5,940 s | 30 min | 95% | 99.0% | 5 | 6 (2.00 d) | 4 |
| 2. Automated Fillet Weld Gantry | 7,200 s | 35 min | 92% | 97.6% | 3 | 5 (1.67 d) | 3 |
| 3. Sectional Weld & Vacuum Test | 9,720 s | 45 min | 84% | 95.4% | 3 | 8 (2.67 d) | 2 |
| 4. Hatch Covers & Winch Mount | 7,020 s | 25 min | 92% | 97.8% | 2 | 4 (1.33 d) | 3 |
| 5. Slipway Launch & Class Approval | 5,580 s | 15 min | 95% | 98.9% | 2 | 3 (1.00 d) | 4 |
Key figures
- Takt time
- 9,000 s
- Lead time
- 11.6 d
- Value-added time
- 35,460 s
- Process cycle efficiency (PCE)
- 11.3%
- Rolled throughput yield (RTY)
- 89.2%
- Customer demand per day
- 3 units
- Line capacity per day
- 2 units
- Bottleneck
- Sectional Weld & Vacuum Test
Reading the bottleneck
The bottleneck is "Sectional Weld & Vacuum Test": it can process 2 units per day against a demand of 3 units, so it falls short of demand by 33.2%. Once downtime and scrap are counted, its cycle time grows from 9,720 s to 12,129 s, against a takt of 9,000 s. The largest loss at this step is equipment downtime (uptime 84%), about 1,851 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Shipbuilding, Rail Rolling Stock & Heavy: Shipbuilding, Rail Rolling Stock & Heavy
- LNG Carrier Double-Hull Steel Block Assembly
- Offshore Wind 4-Legged Steel Jacket Foundation
- 11-Meter XXL Offshore Wind Monopile Rolling Line
- Intermodal 90ft Articulated Rail Container Wagon
- 75m Superyacht Custom Interior Outfitting Bay
- ASME Sec-VIII Petrochemical Hydrocracker Reactor
- Container Vessel Drydock Hull Silane Coating Flow
- 5-Blade 9-Meter Ni-Al-Bronze Ship Propeller
- 500-Ton Canal Lock Mitre Gate Overhaul Yard
- 1,200-Ton Shipyard Goliath Bridge Crane Erection
- Cutter-Suction Harbor Dredger Cutterhead Rebuild