Offshore Wind 4-Legged Steel Jacket Foundation
Product family: 1200T North Sea Steel Structures.
Flow: S355G10+N Heavy Tubular → Heavy Roll & Sub-Arc Can Weld → Multi-Brace Cast Node Fit-Up → PWHT Stress Relief & PAUT NDT → Splash-Zone Metallizing Coat → Skid Load-Out onto Barge → North Sea Offshore Yards
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Heavy Roll & Sub-Arc Can Weld | 17,820 s | 30 min | 95% | 99.0% | 3 | 4 (2.00 d) | 3 |
| 2. Multi-Brace Cast Node Fit-Up | 21,600 s | 35 min | 92% | 97.6% | 2 | 4 (2.00 d) | 2 |
| 3. PWHT Stress Relief & PAUT NDT | 29,160 s | 45 min | 84% | 95.4% | 2 | 5 (2.50 d) | 1 |
| 4. Splash-Zone Metallizing Coat | 21,060 s | 25 min | 92% | 97.8% | 2 | 3 (1.50 d) | 2 |
| 5. Skid Load-Out onto Barge | 16,740 s | 15 min | 95% | 98.9% | 1 | 2 (1.00 d) | 3 |
Key figures
- Takt time
- 27,000 s
- Lead time
- 12.5 d
- Value-added time
- 106,380 s
- Process cycle efficiency (PCE)
- 15.8%
- Rolled throughput yield (RTY)
- 89.2%
- Customer demand per day
- 2 assemblies
- Line capacity per day
- 1 assemblies
- Bottleneck
- PWHT Stress Relief & PAUT NDT
Reading the bottleneck
The bottleneck is "PWHT Stress Relief & PAUT NDT": it can process 1 assemblies per day against a demand of 2 assemblies, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 29,160 s to 36,388 s, against a takt of 27,000 s. The largest loss at this step is equipment downtime (uptime 84%), about 5,554 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Shipbuilding, Rail Rolling Stock & Heavy: Shipbuilding, Rail Rolling Stock & Heavy
- LNG Carrier Double-Hull Steel Block Assembly
- 11-Meter XXL Offshore Wind Monopile Rolling Line
- Intermodal 90ft Articulated Rail Container Wagon
- 75m Superyacht Custom Interior Outfitting Bay
- ASME Sec-VIII Petrochemical Hydrocracker Reactor
- Container Vessel Drydock Hull Silane Coating Flow
- 5-Blade 9-Meter Ni-Al-Bronze Ship Propeller
- Inland River Double-Hull Hopper Cargo Barge
- 500-Ton Canal Lock Mitre Gate Overhaul Yard
- 1,200-Ton Shipyard Goliath Bridge Crane Erection
- Cutter-Suction Harbor Dredger Cutterhead Rebuild