Blue-Laser Metrology Handheld 3D Scanner

Product family: 0.02mm Industrial 3D Scanners.

Flow: Carbon Frame & Global CMOS → Carbon Rigid Stereo Frame → Dual Global-Shutter Camera → Cross-Line Blue Laser Mount → Thermally Stable Bond Cure → NIST Sphere Volumetric Calib → Auto & Aero Quality Labs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Blue-Laser Metrology Handheld 3D ScannerSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Carbon Frame & Global CMOS → Carbon Rigid Stereo Frame (230 s) → Dual Global-Shutter Camera (302 s) → Cross-Line Blue Laser Mount (385 s) → Thermally Stable Bond Cure (266 s) → NIST Sphere Volumetric Calib (202 s) → Auto & Aero Quality Labs.SUPPLIERCarbon Frame &Global CMOSI1.31 d1Carbon RigidStereo FrameC/T 230 sI1.20 d2DualGlobal-Shutter…C/T 302 sI1.60 d3Cross-Line BlueLaser MountC/T 385 sI0.91 d4Thermally StableBond CureC/T 266 sI0.71 d5NIST SphereVolumetric CalibC/T 202 sI1.51 dCUSTOMERAuto & AeroQuality Labs75 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Carbon Rigid Stereo Frame230 s15 min96%98.9%4598 (1.31 d)105
2. Dual Global-Shutter Camera302 s12 min93%97.6%2390 (1.20 d)74
3. Cross-Line Blue Laser Mount385 s15 min86%95.2%19120 (1.60 d)50
4. Thermally Stable Bond Cure266 s8 min95%98.8%1968 (0.91 d)89
5. NIST Sphere Volumetric Calib202 s6 min98%99.6%1553 (0.71 d)122

Key figures

Takt time
360 s
Lead time
7.28 d
Value-added time
1,385 s
Process cycle efficiency (PCE)
0.70%
Rolled throughput yield (RTY)
90.4%
Customer demand per day
75 units
Line capacity per day
50 units
Bottleneck
Cross-Line Blue Laser Mount

Reading the bottleneck

The bottleneck is "Cross-Line Blue Laser Mount": it can process 50 units per day against a demand of 75 units, so it falls short of demand by 33.5%. Once downtime and scrap are counted, its cycle time grows from 385 s to 470 s, against a takt of 360 s. The largest loss at this step is equipment downtime (uptime 86%), about 62.7 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.