ISO-15197 Connected Bluetooth Blood Glucometer
Product family: Pocket Amperometric Readers.
Flow: Analog Front-End Chips → Medical ABS Shell Molding → Low-Leakage Strip Socket SMT → LCD Glass & Elastomer Pad → Control Strip Precision Calib → ISO Accuracy Lot Verify → Pharmacy & Diabetes Care
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Medical ABS Shell Molding | 8.2 s | 15 min | 96% | 98.9% | 2,520 | 5,460 (1.30 d) | 6,079 |
| 2. Low-Leakage Strip Socket SMT | 10.8 s | 12 min | 93% | 97.6% | 1,260 | 5,040 (1.20 d) | 4,337 |
| 3. LCD Glass & Elastomer Pad | 13.8 s | 15 min | 86% | 95.2% | 1,050 | 6,720 (1.60 d) | 2,990 |
| 4. Control Strip Precision Calib | 9.5 s | 8 min | 95% | 98.8% | 1,050 | 3,780 (0.90 d) | 5,146 |
| 5. ISO Accuracy Lot Verify | 7.2 s | 6 min | 98% | 99.6% | 840 | 2,940 (0.70 d) | 7,077 |
Key figures
- Takt time
- 12.9 s
- Lead time
- 7.20 d
- Value-added time
- 49.5 s
- Process cycle efficiency (PCE)
- 0.013%
- Rolled throughput yield (RTY)
- 90.4%
- Customer demand per day
- 4,200 units
- Line capacity per day
- 2,990 units
- Bottleneck
- LCD Glass & Elastomer Pad
Reading the bottleneck
The bottleneck is "LCD Glass & Elastomer Pad": it can process 2,990 units per day against a demand of 4,200 units, so it falls short of demand by 28.8%. Once downtime and scrap are counted, its cycle time grows from 13.8 s to 16.9 s, against a takt of 12.9 s. The largest loss at this step is equipment downtime (uptime 86%), about 2.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Smart Devices, POS & Wearables: Smart Devices, POS & Wearables
- IP68 ATEX Field Rugged Enterprise Tablet
- Hybrid Active Noise-Canceling Over-Ear Headset
- 45MP Full-Frame IBIS Mirrorless Camera Body
- Sapphire-Glass ECG Biomedical Smartwatch Line
- 2D Area-Imager Rugged Warehouse RF Scanner
- 80mm High-Speed Cutter POS Receipt Printer
- Vapor-Chamber Liquid-Metal Pro Laptop Line
- Blue-Laser Metrology Handheld 3D Scanner
- Matter Wi-Fi Aluminum Smart HVAC Thermostat
- 24/7 High-Bright 3500-Nit Digital Totem Display
- IP68 Titanium Bone-Conduction Sport Headset