High-Power 976nm Fiber-Coupled Pump Diode
Product family: 150W Industrial Fiber Lasers.
Flow: GaAs Laser Bars → Indium/AuSn Bar Bonding → Fast-Axis Micro-Lens Collim → Multi-Emitter Knife Prism → 105um Fiber Coupling Align → 48h LIV Optical Power Burn → Fiber Laser Cutting OEMs
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Indium/AuSn Bar Bonding | 150 s | 30 min | 94% | 97.8% | 260 | 468 (1.80 d) | 320 |
| 2. Fast-Axis Micro-Lens Collim | 174 s | 45 min | 90% | 96.5% | 312 | 494 (1.90 d) | 258 |
| 3. Multi-Emitter Knife Prism | 224 s | 25 min | 84% | 93.8% | 130 | 546 (2.10 d) | 179 |
| 4. 105um Fiber Coupling Align | 158 s | 15 min | 95% | 98.4% | 78 | 260 (1.00 d) | 302 |
| 5. 48h LIV Optical Power Burn | 125 s | 8 min | 97% | 99.1% | 52 | 182 (0.70 d) | 397 |
Key figures
- Takt time
- 208 s
- Lead time
- 8.72 d
- Value-added time
- 831 s
- Process cycle efficiency (PCE)
- 0.18%
- Rolled throughput yield (RTY)
- 86.3%
- Customer demand per day
- 260 units
- Line capacity per day
- 179 units
- Bottleneck
- Multi-Emitter Knife Prism
Reading the bottleneck
The bottleneck is "Multi-Emitter Knife Prism": it can process 179 units per day against a demand of 260 units, so it falls short of demand by 31.0%. Once downtime and scrap are counted, its cycle time grows from 224 s to 284 s, against a takt of 208 s. The largest loss at this step is equipment downtime (uptime 84%), about 42.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Optics, Photonics & Precision Sensors: Optics, Photonics & Precision Sensors
- 400G OSFP / QSFP-DD Optical Transceiver
- 4K Chip-on-Tip Surgical Laparoscope Optics
- 1550nm Long-Range Automotive Roof LiDAR
- 640x512 Uncooled VOx LWIR Thermal Camera Core
- Plan-Apochromat 100x Oil Objective Assembly
- 128-Element Phased-Array Ultrasound Probe
- N-Type TOPCon Bifacial Solar Cell Fab Line
- Piezoresistive 316L Hygienic Pressure Transmitter
- Twin-Bent-Tube Coriolis Mass Flowmeter
- Holographic Diffraction Spectroscopic Grating
- Adaptive Pixel-LED Automotive Headlamp Matrix