Piezoresistive 316L Hygienic Pressure Transmitter

Product family: HART / IO-Link Process Sensors.

Flow: Silicon Sensor Die Suppliers → SS Diaphragm Electron Beam → Oil-Fill Vacuum Capillaries → Signal Condition HART Board → M12 Connector Laser Weld → Tri-Temp Full Span Calibrate → Food & Pharma Process Skids

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Piezoresistive 316L Hygienic Pressure TransmitterSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Silicon Sensor Die Suppliers → SS Diaphragm Electron Beam (50.0 s) → Oil-Fill Vacuum Capillaries (58.0 s) → Signal Condition HART Board (75.0 s) → M12 Connector Laser Weld (53.0 s) → Tri-Temp Full Span Calibrate (42.0 s) → Food & Pharma Process Skids.SUPPLIERSilicon SensorDie SuppliersI1.80 d1SS DiaphragmElectron BeamC/T 50.0 sI1.90 d2Oil-Fill VacuumCapillariesC/T 58.0 sI2.10 d3Signal ConditionHART BoardC/T 75.0 sI1.00 d4M12 ConnectorLaser WeldC/T 53.0 sI0.70 d5Tri-Temp FullSpan CalibrateC/T 42.0 sI1.20 dCUSTOMERFood & PharmaProcess Skids780 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. SS Diaphragm Electron Beam50.0 s30 min94%97.8%7801,404 (1.80 d)960
2. Oil-Fill Vacuum Capillaries58.0 s45 min90%96.5%9361,482 (1.90 d)775
3. Signal Condition HART Board75.0 s25 min84%93.8%3901,638 (2.10 d)536
4. M12 Connector Laser Weld53.0 s15 min95%98.4%234780 (1.00 d)900
5. Tri-Temp Full Span Calibrate42.0 s8 min97%99.1%156546 (0.70 d)1,181

Key figures

Takt time
69.2 s
Lead time
8.71 d
Value-added time
278 s
Process cycle efficiency (PCE)
0.059%
Rolled throughput yield (RTY)
86.3%
Customer demand per day
780 units
Line capacity per day
536 units
Bottleneck
Signal Condition HART Board

Reading the bottleneck

The bottleneck is "Signal Condition HART Board": it can process 536 units per day against a demand of 780 units, so it falls short of demand by 31.3%. Once downtime and scrap are counted, its cycle time grows from 75.0 s to 95.2 s, against a takt of 69.2 s. The largest loss at this step is equipment downtime (uptime 84%), about 14.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.