400G OSFP / QSFP-DD Optical Transceiver

Product family: Silicon Photonics Data Links.

Flow: Silicon Photonics Wafers → Laser Chip Eutectic Die Bond → Micro-Lens Active Coupling → High-Speed RF PCB Wirebond → Die-Cast Latch Housing Snap → BERT Bit-Error-Rate 400G → Cloud Switch Builders

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 400G OSFP / QSFP-DD Optical TransceiverSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Silicon Photonics Wafers → Laser Chip Eutectic Die Bond (32.4 s) → Micro-Lens Active Coupling (37.8 s) → High-Speed RF PCB Wirebond (49.0 s) → Die-Cast Latch Housing Snap (34.2 s) → BERT Bit-Error-Rate 400G (27.0 s) → Cloud Switch Builders.SUPPLIERSiliconPhotonicsWafersI1.80 d1Laser ChipEutectic Die BondC/T 32.4 sI1.90 d2Micro-Lens ActiveCouplingC/T 37.8 sI2.10 d3High-Speed RF PCBWirebondC/T 49.0 sI1.00 d4Die-Cast LatchHousing SnapC/T 34.2 sI0.70 d5BERTBit-Error-Rate…C/T 27.0 sI1.20 dCUSTOMERCloud SwitchBuilders1,800 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Laser Chip Eutectic Die Bond32.4 s30 min94%97.8%1,8003,240 (1.80 d)2,247
2. Micro-Lens Active Coupling37.8 s45 min90%96.5%2,1603,420 (1.90 d)1,809
3. High-Speed RF PCB Wirebond49.0 s25 min84%93.8%9003,780 (2.10 d)1,254
4. Die-Cast Latch Housing Snap34.2 s15 min95%98.4%5401,800 (1.00 d)2,132
5. BERT Bit-Error-Rate 400G27.0 s8 min97%99.1%3601,260 (0.70 d)2,798

Key figures

Takt time
45.0 s
Lead time
8.70 d
Value-added time
180 s
Process cycle efficiency (PCE)
0.026%
Rolled throughput yield (RTY)
86.3%
Customer demand per day
1,800 units
Line capacity per day
1,254 units
Bottleneck
High-Speed RF PCB Wirebond

Reading the bottleneck

The bottleneck is "High-Speed RF PCB Wirebond": it can process 1,254 units per day against a demand of 1,800 units, so it falls short of demand by 30.3%. Once downtime and scrap are counted, its cycle time grows from 49.0 s to 62.2 s, against a takt of 45.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 9.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Optics, Photonics & Precision Sensors: Optics, Photonics & Precision Sensors