Plan-Apochromat 100x Oil Objective Assembly

Product family: Sub-Nanometer Lab Objectives.

Flow: Fluorite Optical Glass → Precision Fluorite Lens Polish → Multi-Layer Ion-Beam Coat → Brass Barrel Spacer Shim Fit → Interferometric Wavefront Align → Strehl Ratio >0.96 Sign-Off → Bio-Pharma Microscopy

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Plan-Apochromat 100x Oil Objective AssemblySupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Fluorite Optical Glass → Precision Fluorite Lens Polish (229 s) → Multi-Layer Ion-Beam Coat (267 s) → Brass Barrel Spacer Shim Fit (343 s) → Interferometric Wavefront Align (241 s) → Strehl Ratio >0.96 Sign-Off (191 s) → Bio-Pharma Microscopy.SUPPLIERFluoriteOptical GlassI1.80 d1PrecisionFluorite Lens…C/T 229 sI1.91 d2Multi-LayerIon-Beam CoatC/T 267 sI2.11 d3Brass BarrelSpacer Shim FitC/T 343 sI1.00 d4InterferometricWavefront AlignC/T 241 sI0.69 d5Strehl Ratio>0.96 Sign-OffC/T 191 sI1.20 dCUSTOMERBio-PharmaMicroscopy85 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Precision Fluorite Lens Polish229 s30 min94%97.8%85153 (1.80 d)101
2. Multi-Layer Ion-Beam Coat267 s45 min90%96.5%102162 (1.91 d)81
3. Brass Barrel Spacer Shim Fit343 s25 min84%93.8%43179 (2.11 d)55
4. Interferometric Wavefront Align241 s15 min95%98.4%2685 (1.00 d)93
5. Strehl Ratio >0.96 Sign-Off191 s8 min97%99.1%1759 (0.69 d)124

Key figures

Takt time
318 s
Lead time
8.75 d
Value-added time
1,271 s
Process cycle efficiency (PCE)
0.54%
Rolled throughput yield (RTY)
86.3%
Customer demand per day
85 units
Line capacity per day
55 units
Bottleneck
Brass Barrel Spacer Shim Fit

Reading the bottleneck

The bottleneck is "Brass Barrel Spacer Shim Fit": it can process 55 units per day against a demand of 85 units, so it falls short of demand by 35.0%. Once downtime and scrap are counted, its cycle time grows from 343 s to 435 s, against a takt of 318 s. The largest loss at this step is equipment downtime (uptime 84%), about 65.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.