128-Element Phased-Array Ultrasound Probe
Product family: PZT Piezo Clinical Transducers.
Flow: Piezo Ceramic Suppliers → PZT Kerf Diamond Dicing → Quarter-Wave Acoustic Match → 128-Ch Micro-Coax Solder → RTV Silicone Lens Pour → Pulse-Echo Sensitivity Map → Hospital Ultrasound Systems
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. PZT Kerf Diamond Dicing | 353 s | 30 min | 94% | 97.8% | 110 | 198 (1.80 d) | 136 |
| 2. Quarter-Wave Acoustic Match | 412 s | 45 min | 90% | 96.5% | 132 | 209 (1.90 d) | 109 |
| 3. 128-Ch Micro-Coax Solder | 530 s | 25 min | 84% | 93.8% | 55 | 231 (2.10 d) | 76 |
| 4. RTV Silicone Lens Pour | 373 s | 15 min | 95% | 98.4% | 33 | 110 (1.00 d) | 128 |
| 5. Pulse-Echo Sensitivity Map | 295 s | 8 min | 97% | 99.1% | 22 | 77 (0.70 d) | 168 |
Key figures
- Takt time
- 491 s
- Lead time
- 8.74 d
- Value-added time
- 1,963 s
- Process cycle efficiency (PCE)
- 0.42%
- Rolled throughput yield (RTY)
- 86.3%
- Customer demand per day
- 110 units
- Line capacity per day
- 76 units
- Bottleneck
- 128-Ch Micro-Coax Solder
Reading the bottleneck
The bottleneck is "128-Ch Micro-Coax Solder": it can process 76 units per day against a demand of 110 units, so it falls short of demand by 31.1%. Once downtime and scrap are counted, its cycle time grows from 530 s to 673 s, against a takt of 491 s. The largest loss at this step is equipment downtime (uptime 84%), about 101 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Optics, Photonics & Precision Sensors: Optics, Photonics & Precision Sensors
- 400G OSFP / QSFP-DD Optical Transceiver
- 4K Chip-on-Tip Surgical Laparoscope Optics
- 1550nm Long-Range Automotive Roof LiDAR
- 640x512 Uncooled VOx LWIR Thermal Camera Core
- Plan-Apochromat 100x Oil Objective Assembly
- N-Type TOPCon Bifacial Solar Cell Fab Line
- High-Power 976nm Fiber-Coupled Pump Diode
- Piezoresistive 316L Hygienic Pressure Transmitter
- Twin-Bent-Tube Coriolis Mass Flowmeter
- Holographic Diffraction Spectroscopic Grating
- Adaptive Pixel-LED Automotive Headlamp Matrix