220kV Air-Insulated Grid Substation Bay Build
Product family: Turnkey Transmission Bays.
Flow: GIS/AIS Breakers & PTs → Civil Foundation & Ground Grid → Portal Gantry & Isolator Rig → SF6-Free Circuit Breaker Tie → Fiber IEC-61850 Relay Patch → HiPot & Grid SCADA Energize → National Transmission TSOs
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Civil Foundation & Ground Grid | 4,455 s | 15 min | 96% | 95.8% | 1 | 7 (1.75 d) | 5 |
| 2. Portal Gantry & Isolator Rig | 5,265 s | 20 min | 93% | 97.6% | 2 | 6 (1.50 d) | 4 |
| 3. SF6-Free Circuit Breaker Tie | 7,290 s | 30 min | 85% | 94.5% | 1 | 9 (2.25 d) | 3 |
| 4. Fiber IEC-61850 Relay Patch | 5,130 s | 12 min | 94% | 97.8% | 1 | 4 (1.00 d) | 5 |
| 5. HiPot & Grid SCADA Energize | 3,375 s | 5 min | 98% | 99.4% | 1 | 2 (0.50 d) | 8 |
Key figures
- Takt time
- 6,750 s
- Lead time
- 8.45 d
- Value-added time
- 25,515 s
- Process cycle efficiency (PCE)
- 11.2%
- Rolled throughput yield (RTY)
- 85.9%
- Customer demand per day
- 4 cases
- Line capacity per day
- 3 cases
- Bottleneck
- SF6-Free Circuit Breaker Tie
Reading the bottleneck
The bottleneck is "SF6-Free Circuit Breaker Tie": it can process 3 cases per day against a demand of 4 cases, so it falls short of demand by 30.6%. Once downtime and scrap are counted, its cycle time grows from 7,290 s to 9,076 s, against a takt of 6,750 s. The largest loss at this step is changeovers (30 min every 1 units), about 1,800 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Power Grids, Substations & Smart Metering: Power Grids, Substations & Smart Metering
- Mass AMI Smart Electricity Meter Swap Route
- 63kV Overhead Aluminum HTLS Reconductoring
- 110kV XLPE Underground Cable Splice & HiPot
- Storm Distribution Feeder Fault Isolation & Restore
- PWR Nuclear Power Plant Refueling Outage (RFO)
- 450MW Gas Turbine Hot-Gas-Path Inspection
- Electric Bus Depot 3MW Grid Transformer Upgrade
- 2GW Offshore HVDC Converter Thyristor Maintenance
- Municipal Streetlight Zhaga-D4i Smart LED Retro
- Substation IEC-61850 Protection Relay Maintenance
- Industrial Islandable Solar+Genset Microgrid