220kV Air-Insulated Grid Substation Bay Build

Product family: Turnkey Transmission Bays.

Flow: GIS/AIS Breakers & PTs → Civil Foundation & Ground Grid → Portal Gantry & Isolator Rig → SF6-Free Circuit Breaker Tie → Fiber IEC-61850 Relay Patch → HiPot & Grid SCADA Energize → National Transmission TSOs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 220kV Air-Insulated Grid Substation Bay BuildSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. GIS/AIS Breakers & PTs → Civil Foundation & Ground Grid (4,455 s) → Portal Gantry & Isolator Rig (5,265 s) → SF6-Free Circuit Breaker Tie (7,290 s) → Fiber IEC-61850 Relay Patch (5,130 s) → HiPot & Grid SCADA Energize (3,375 s) → National Transmission TSOs.SUPPLIERGIS/AISBreakers & PTsI1.75 d1Civil Foundation& Ground GridC/T 4,455 sI1.50 d2Portal Gantry &Isolator RigC/T 5,265 sI2.25 d3SF6-Free CircuitBreaker TieC/T 7,290 sI1.00 d4Fiber IEC-61850Relay PatchC/T 5,130 sI0.50 d5HiPot & GridSCADA EnergizeC/T 3,375 sI0.50 dCUSTOMERNationalTransmission…4 / cases

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Civil Foundation & Ground Grid4,455 s15 min96%95.8%17 (1.75 d)5
2. Portal Gantry & Isolator Rig5,265 s20 min93%97.6%26 (1.50 d)4
3. SF6-Free Circuit Breaker Tie7,290 s30 min85%94.5%19 (2.25 d)3
4. Fiber IEC-61850 Relay Patch5,130 s12 min94%97.8%14 (1.00 d)5
5. HiPot & Grid SCADA Energize3,375 s5 min98%99.4%12 (0.50 d)8

Key figures

Takt time
6,750 s
Lead time
8.45 d
Value-added time
25,515 s
Process cycle efficiency (PCE)
11.2%
Rolled throughput yield (RTY)
85.9%
Customer demand per day
4 cases
Line capacity per day
3 cases
Bottleneck
SF6-Free Circuit Breaker Tie

Reading the bottleneck

The bottleneck is "SF6-Free Circuit Breaker Tie": it can process 3 cases per day against a demand of 4 cases, so it falls short of demand by 30.6%. Once downtime and scrap are counted, its cycle time grows from 7,290 s to 9,076 s, against a takt of 6,750 s. The largest loss at this step is changeovers (30 min every 1 units), about 1,800 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Power Grids, Substations & Smart Metering: Power Grids, Substations & Smart Metering