450MW Gas Turbine Hot-Gas-Path Inspection

Product family: Fast-Track Peak Grid Turnaround.

Flow: OEM Coated Turbine Blades → Barring Gear Cool & Casings Off → Row 1–3 Bucket Pull & FPI → Combustor Transition Swap → Top-Case Laser Center Torque → Overspeed Trip & Base Sync → Utility Combined-Cycle Plants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 450MW Gas Turbine Hot-Gas-Path InspectionSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. OEM Coated Turbine Blades → Barring Gear Cool & Casings Off (17,820 s) → Row 1–3 Bucket Pull & FPI (21,060 s) → Combustor Transition Swap (29,160 s) → Top-Case Laser Center Torque (20,520 s) → Overspeed Trip & Base Sync (13,500 s) → Utility Combined-Cycle Plants.SUPPLIEROEM CoatedTurbine BladesI2.00 d1Barring Gear Cool& Casings OffC/T 17,820 sI1.50 d2Row 1–3 BucketPull & FPIC/T 21,060 sI2.00 d3CombustorTransition SwapC/T 29,160 sI1.00 d4Top-Case LaserCenter TorqueC/T 20,520 sI0.50 d5Overspeed Trip &Base SyncC/T 13,500 sI0.50 dCUSTOMERUtilityCombined-Cycle…2 / cases

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Barring Gear Cool & Casings Off17,820 s15 min96%95.8%14 (2.00 d)3
2. Row 1–3 Bucket Pull & FPI21,060 s20 min93%97.6%13 (1.50 d)2
3. Combustor Transition Swap29,160 s30 min85%94.5%14 (2.00 d)1
4. Top-Case Laser Center Torque20,520 s12 min94%97.8%12 (1.00 d)2
5. Overspeed Trip & Base Sync13,500 s5 min98%99.4%11 (0.50 d)4

Key figures

Takt time
27,000 s
Lead time
9.39 d
Value-added time
102,060 s
Process cycle efficiency (PCE)
20.1%
Rolled throughput yield (RTY)
85.9%
Customer demand per day
2 cases
Line capacity per day
1 cases
Bottleneck
Combustor Transition Swap

Reading the bottleneck

The bottleneck is "Combustor Transition Swap": it can process 1 cases per day against a demand of 2 cases, so it falls short of demand by 28.1%. Once downtime and scrap are counted, its cycle time grows from 29,160 s to 36,303 s, against a takt of 27,000 s. The largest loss at this step is equipment downtime (uptime 85%), about 5,146 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.