450MW Gas Turbine Hot-Gas-Path Inspection
Product family: Fast-Track Peak Grid Turnaround.
Flow: OEM Coated Turbine Blades → Barring Gear Cool & Casings Off → Row 1–3 Bucket Pull & FPI → Combustor Transition Swap → Top-Case Laser Center Torque → Overspeed Trip & Base Sync → Utility Combined-Cycle Plants
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Barring Gear Cool & Casings Off | 17,820 s | 15 min | 96% | 95.8% | 1 | 4 (2.00 d) | 3 |
| 2. Row 1–3 Bucket Pull & FPI | 21,060 s | 20 min | 93% | 97.6% | 1 | 3 (1.50 d) | 2 |
| 3. Combustor Transition Swap | 29,160 s | 30 min | 85% | 94.5% | 1 | 4 (2.00 d) | 1 |
| 4. Top-Case Laser Center Torque | 20,520 s | 12 min | 94% | 97.8% | 1 | 2 (1.00 d) | 2 |
| 5. Overspeed Trip & Base Sync | 13,500 s | 5 min | 98% | 99.4% | 1 | 1 (0.50 d) | 4 |
Key figures
- Takt time
- 27,000 s
- Lead time
- 9.39 d
- Value-added time
- 102,060 s
- Process cycle efficiency (PCE)
- 20.1%
- Rolled throughput yield (RTY)
- 85.9%
- Customer demand per day
- 2 cases
- Line capacity per day
- 1 cases
- Bottleneck
- Combustor Transition Swap
Reading the bottleneck
The bottleneck is "Combustor Transition Swap": it can process 1 cases per day against a demand of 2 cases, so it falls short of demand by 28.1%. Once downtime and scrap are counted, its cycle time grows from 29,160 s to 36,303 s, against a takt of 27,000 s. The largest loss at this step is equipment downtime (uptime 85%), about 5,146 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Power Grids, Substations & Smart Metering: Power Grids, Substations & Smart Metering
- 220kV Air-Insulated Grid Substation Bay Build
- Mass AMI Smart Electricity Meter Swap Route
- 63kV Overhead Aluminum HTLS Reconductoring
- 110kV XLPE Underground Cable Splice & HiPot
- Storm Distribution Feeder Fault Isolation & Restore
- PWR Nuclear Power Plant Refueling Outage (RFO)
- Electric Bus Depot 3MW Grid Transformer Upgrade
- 2GW Offshore HVDC Converter Thyristor Maintenance
- Municipal Streetlight Zhaga-D4i Smart LED Retro
- Substation IEC-61850 Protection Relay Maintenance
- Industrial Islandable Solar+Genset Microgrid