Direct Lithium Extraction (DLE) & Li2CO3 Plant
Product family: 99.5% Battery-Grade Carbonate.
Flow: Salars Brine Injection Wells → Raw Brine Filter & Silica Trap → DLE Ion-Sieve Adsorption Skid → Nanofiltration & RO Concentrate → Soda-Ash Crystallizer Wash → Fine Jet-Mill & 500kg Bag → EV Cathode Refineries
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Raw Brine Filter & Silica Trap | 614 s | 10 min | 92% | 98.8% | 95 | 133 (1.40 d) | 119 |
| 2. DLE Ion-Sieve Adsorption Skid | 921 s | 35 min | 81% | 95.0% | 95 | 209 (2.20 d) | 66 |
| 3. Nanofiltration & RO Concentrate | 716 s | 20 min | 91% | 97.2% | 76 | 152 (1.60 d) | 98 |
| 4. Soda-Ash Crystallizer Wash | 597 s | 10 min | 95% | 98.4% | 38 | 95 (1.00 d) | 124 |
| 5. Fine Jet-Mill & 500kg Bag | 477 s | 8 min | 97% | 99.4% | 38 | 114 (1.20 d) | 161 |
Key figures
- Takt time
- 853 s
- Lead time
- 8.84 d
- Value-added time
- 3,325 s
- Process cycle efficiency (PCE)
- 0.46%
- Rolled throughput yield (RTY)
- 89.2%
- Customer demand per day
- 95 tonnes
- Line capacity per day
- 66 tonnes
- Bottleneck
- DLE Ion-Sieve Adsorption Skid
Reading the bottleneck
The bottleneck is "DLE Ion-Sieve Adsorption Skid": it can process 66 tonnes per day against a demand of 95 tonnes, so it falls short of demand by 30.6%. Once downtime and scrap are counted, its cycle time grows from 921 s to 1,197 s, against a takt of 853 s. The largest loss at this step is equipment downtime (uptime 81%), about 216 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Mining, Quarries, Lithium & Refining: Mining, Quarries, Lithium & Refining
- Crushing, Screening & Bulk Rail Dispatch
- 60,000-TPD Copper Porphyry SAG Mill & Flotation
- Carbon-in-Leach (CIL) Gold Ore Extraction
- Phosphate Ore Calcination, Scrub & Pipeline
- Magnetite Iron Ore Concentrator & Induration
- Caustic Bauxite Digestion to Smelter Alumina
- Exploration Diamond Core Logging & Fire-Assay Lab
- 240-Ton Electric Haul Truck 15,000-Hr Overhaul
- Automated Autonomous Drill-Blast-Load Mine Bench
- Granular Muriate of Potash (MOP) Compaction
- Solar Sea-Salt Wash, Vacuum Evaporate & Iodize