Magnetite Iron Ore Concentrator & Induration

Product family: 67% Fe Direct-Reduction Pellets.

Flow: Banded Iron Formation Pit → HPGR High-Press Grinding Roll → Low-Intensity Magnetic Sep → Vacuum Disc Filter & Bentonite → Balling Disc Green Pellets → 1300°C Traveling Grate Indur → DRI Green Steel Furnaces

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Magnetite Iron Ore Concentrator & IndurationSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Banded Iron Formation Pit → HPGR High-Press Grinding Roll (69.0 s) → Low-Intensity Magnetic Sep (103 s) → Vacuum Disc Filter & Bentonite (80.0 s) → Balling Disc Green Pellets (67.0 s) → 1300°C Traveling Grate Indur (53.0 s) → DRI Green Steel Furnaces.SUPPLIERBanded IronFormation PitI1.40 d1HPGR High-PressGrinding RollC/T 69.0 sI2.20 d2Low-IntensityMagnetic SepC/T 103 sI1.60 d3Vacuum DiscFilter &…C/T 80.0 sI1.00 d4Balling DiscGreen PelletsC/T 67.0 sI1.20 d51300°C TravelingGrate IndurC/T 53.0 sI1.40 dCUSTOMERDRI Green SteelFurnaces850 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. HPGR High-Press Grinding Roll69.0 s10 min92%98.8%8501,190 (1.40 d)1,059
2. Low-Intensity Magnetic Sep103 s35 min81%95.0%8501,870 (2.20 d)589
3. Vacuum Disc Filter & Bentonite80.0 s20 min91%97.2%6801,360 (1.60 d)879
4. Balling Disc Green Pellets67.0 s10 min95%98.4%340850 (1.00 d)1,109
5. 1300°C Traveling Grate Indur53.0 s8 min97%99.4%3401,020 (1.20 d)1,452

Key figures

Takt time
95.3 s
Lead time
8.80 d
Value-added time
372 s
Process cycle efficiency (PCE)
0.052%
Rolled throughput yield (RTY)
89.2%
Customer demand per day
850 tonnes
Line capacity per day
589 tonnes
Bottleneck
Low-Intensity Magnetic Sep

Reading the bottleneck

The bottleneck is "Low-Intensity Magnetic Sep": it can process 589 tonnes per day against a demand of 850 tonnes, so it falls short of demand by 30.7%. Once downtime and scrap are counted, its cycle time grows from 103 s to 134 s, against a takt of 95.3 s. The largest loss at this step is equipment downtime (uptime 81%), about 24.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Mining, Quarries, Lithium & Refining: Mining, Quarries, Lithium & Refining