Crushing, Screening & Bulk Rail Dispatch
Product family: Graded Mineral & Aggregate Tonnage.
Flow: Active Quarry Pit Benches → Pit Haul & Dump Hopper → Jaw Crusher & Screening → Washing & Lab Assay → Stockpile Conveyors → Silo Rail Weighbridge → Cement & Infrastructure Plants
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Pit Haul & Dump Hopper | 144 s | 10 min | 92% | 98.8% | 270 | 378 (1.40 d) | 337 |
| 2. Jaw Crusher & Screening | 216 s | 35 min | 81% | 95.0% | 270 | 594 (2.20 d) | 185 |
| 3. Washing & Lab Assay | 168 s | 20 min | 91% | 97.2% | 216 | 432 (1.60 d) | 276 |
| 4. Stockpile Conveyors | 140 s | 10 min | 95% | 98.4% | 108 | 270 (1.00 d) | 351 |
| 5. Silo Rail Weighbridge | 112 s | 8 min | 97% | 99.4% | 108 | 324 (1.20 d) | 455 |
Key figures
- Takt time
- 200 s
- Lead time
- 8.81 d
- Value-added time
- 780 s
- Process cycle efficiency (PCE)
- 0.16%
- Rolled throughput yield (RTY)
- 89.2%
- Customer demand per day
- 270 batches
- Line capacity per day
- 185 batches
- Bottleneck
- Jaw Crusher & Screening
Reading the bottleneck
The bottleneck is "Jaw Crusher & Screening": it can process 185 batches per day against a demand of 270 batches, so it falls short of demand by 31.5%. Once downtime and scrap are counted, its cycle time grows from 216 s to 281 s, against a takt of 200 s. The largest loss at this step is equipment downtime (uptime 81%), about 50.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Mining, Quarries, Lithium & Refining: Mining, Quarries, Lithium & Refining
- 60,000-TPD Copper Porphyry SAG Mill & Flotation
- Carbon-in-Leach (CIL) Gold Ore Extraction
- Phosphate Ore Calcination, Scrub & Pipeline
- Direct Lithium Extraction (DLE) & Li2CO3 Plant
- Magnetite Iron Ore Concentrator & Induration
- Caustic Bauxite Digestion to Smelter Alumina
- Exploration Diamond Core Logging & Fire-Assay Lab
- 240-Ton Electric Haul Truck 15,000-Hr Overhaul
- Automated Autonomous Drill-Blast-Load Mine Bench
- Granular Muriate of Potash (MOP) Compaction
- Solar Sea-Salt Wash, Vacuum Evaporate & Iodize