Caustic Bauxite Digestion to Smelter Alumina
Product family: Calcined Al2O3 Sandy Alumina.
Flow: Tropical Laterite Bauxite → Rod-Mill Caustic Wet Grind → 240°C High-Pressure Digestion → Red Mud Counter-Wash Decant → Seeded Trihydrate Precipitate → 1050°C Gas Fluid Calciner → Aluminum Smelter Potlines
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Rod-Mill Caustic Wet Grind | 81.0 s | 10 min | 92% | 98.8% | 720 | 1,008 (1.40 d) | 902 |
| 2. 240°C High-Pressure Digestion | 122 s | 35 min | 81% | 95.0% | 720 | 1,584 (2.20 d) | 498 |
| 3. Red Mud Counter-Wash Decant | 95.0 s | 20 min | 91% | 97.2% | 576 | 1,152 (1.60 d) | 740 |
| 4. Seeded Trihydrate Precipitate | 79.0 s | 10 min | 95% | 98.4% | 288 | 720 (1.00 d) | 941 |
| 5. 1050°C Gas Fluid Calciner | 63.0 s | 8 min | 97% | 99.4% | 288 | 864 (1.20 d) | 1,221 |
Key figures
- Takt time
- 113 s
- Lead time
- 8.81 d
- Value-added time
- 440 s
- Process cycle efficiency (PCE)
- 0.062%
- Rolled throughput yield (RTY)
- 89.2%
- Customer demand per day
- 720 tonnes
- Line capacity per day
- 498 tonnes
- Bottleneck
- 240°C High-Pressure Digestion
Reading the bottleneck
The bottleneck is "240°C High-Pressure Digestion": it can process 498 tonnes per day against a demand of 720 tonnes, so it falls short of demand by 30.9%. Once downtime and scrap are counted, its cycle time grows from 122 s to 159 s, against a takt of 113 s. The largest loss at this step is equipment downtime (uptime 81%), about 28.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Mining, Quarries, Lithium & Refining: Mining, Quarries, Lithium & Refining
- Crushing, Screening & Bulk Rail Dispatch
- 60,000-TPD Copper Porphyry SAG Mill & Flotation
- Carbon-in-Leach (CIL) Gold Ore Extraction
- Phosphate Ore Calcination, Scrub & Pipeline
- Direct Lithium Extraction (DLE) & Li2CO3 Plant
- Magnetite Iron Ore Concentrator & Induration
- Exploration Diamond Core Logging & Fire-Assay Lab
- 240-Ton Electric Haul Truck 15,000-Hr Overhaul
- Automated Autonomous Drill-Blast-Load Mine Bench
- Granular Muriate of Potash (MOP) Compaction
- Solar Sea-Salt Wash, Vacuum Evaporate & Iodize