Granular Muriate of Potash (MOP) Compaction

Product family: Dust-Free Red/White Granular.

Flow: Underground Room-and-Pillar → Dry Screw Feeder Preheat → Smooth-Roll High-Force Flake → Crusher & Double-Deck Screen → Glazing Drum Steam Moisture → Bulk Covered Hopper Rail Load → Bulk NPK Blending Terminals

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Granular Muriate of Potash (MOP) CompactionSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Underground Room-and-Pillar → Dry Screw Feeder Preheat (112 s) → Smooth-Roll High-Force Flake (168 s) → Crusher & Double-Deck Screen (131 s) → Glazing Drum Steam Moisture (109 s) → Bulk Covered Hopper Rail Load (87.0 s) → Bulk NPK Blending Terminals.SUPPLIERUndergroundRoom-and-PillarI1.40 d1Dry Screw FeederPreheatC/T 112 sI2.20 d2Smooth-RollHigh-Force FlakeC/T 168 sI1.60 d3Crusher &Double-Deck…C/T 131 sI1.00 d4Glazing DrumSteam MoistureC/T 109 sI1.20 d5Bulk CoveredHopper Rail LoadC/T 87.0 sI1.40 dCUSTOMERBulk NPKBlending…520 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Dry Screw Feeder Preheat112 s10 min92%98.8%520728 (1.40 d)653
2. Smooth-Roll High-Force Flake168 s35 min81%95.0%5201,144 (2.20 d)361
3. Crusher & Double-Deck Screen131 s20 min91%97.2%416832 (1.60 d)537
4. Glazing Drum Steam Moisture109 s10 min95%98.4%208520 (1.00 d)682
5. Bulk Covered Hopper Rail Load87.0 s8 min97%99.4%208624 (1.20 d)884

Key figures

Takt time
156 s
Lead time
8.81 d
Value-added time
607 s
Process cycle efficiency (PCE)
0.085%
Rolled throughput yield (RTY)
89.2%
Customer demand per day
520 tonnes
Line capacity per day
361 tonnes
Bottleneck
Smooth-Roll High-Force Flake

Reading the bottleneck

The bottleneck is "Smooth-Roll High-Force Flake": it can process 361 tonnes per day against a demand of 520 tonnes, so it falls short of demand by 30.5%. Once downtime and scrap are counted, its cycle time grows from 168 s to 218 s, against a takt of 156 s. The largest loss at this step is equipment downtime (uptime 81%), about 39.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.