Solar Sea-Salt Wash, Vacuum Evaporate & Iodize
Product family: 99.9% Pure Culinary & Chloralk.
Flow: Coastal Solar Evaporation Pans → Hydrocyclone Counterflow Wash → Fluid-Bed Dryer & Sieve Cut → Potassium Iodate Mist Spray → 1kg Carton / 25kg Poly Pack → X-Ray & Anti-Cake Release → Food, Pharma & Chemical Buyers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Hydrocyclone Counterflow Wash | 114 s | 10 min | 92% | 98.8% | 340 | 476 (1.40 d) | 426 |
| 2. Fluid-Bed Dryer & Sieve Cut | 172 s | 35 min | 81% | 95.0% | 340 | 748 (2.20 d) | 232 |
| 3. Potassium Iodate Mist Spray | 133 s | 20 min | 91% | 97.2% | 272 | 544 (1.60 d) | 349 |
| 4. 1kg Carton / 25kg Poly Pack | 111 s | 10 min | 95% | 98.4% | 136 | 340 (1.00 d) | 442 |
| 5. X-Ray & Anti-Cake Release | 89.0 s | 8 min | 97% | 99.4% | 136 | 408 (1.20 d) | 572 |
Key figures
- Takt time
- 159 s
- Lead time
- 8.81 d
- Value-added time
- 619 s
- Process cycle efficiency (PCE)
- 0.13%
- Rolled throughput yield (RTY)
- 89.2%
- Customer demand per day
- 340 tonnes
- Line capacity per day
- 232 tonnes
- Bottleneck
- Fluid-Bed Dryer & Sieve Cut
Reading the bottleneck
The bottleneck is "Fluid-Bed Dryer & Sieve Cut": it can process 232 tonnes per day against a demand of 340 tonnes, so it falls short of demand by 31.7%. Once downtime and scrap are counted, its cycle time grows from 172 s to 224 s, against a takt of 159 s. The largest loss at this step is equipment downtime (uptime 81%), about 40.3 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Mining, Quarries, Lithium & Refining: Mining, Quarries, Lithium & Refining
- Crushing, Screening & Bulk Rail Dispatch
- 60,000-TPD Copper Porphyry SAG Mill & Flotation
- Carbon-in-Leach (CIL) Gold Ore Extraction
- Phosphate Ore Calcination, Scrub & Pipeline
- Direct Lithium Extraction (DLE) & Li2CO3 Plant
- Magnetite Iron Ore Concentrator & Induration
- Caustic Bauxite Digestion to Smelter Alumina
- Exploration Diamond Core Logging & Fire-Assay Lab
- 240-Ton Electric Haul Truck 15,000-Hr Overhaul
- Automated Autonomous Drill-Blast-Load Mine Bench
- Granular Muriate of Potash (MOP) Compaction