2,400-cph LPG Domestic Gas Cylinder Hydro & Fill
Product family: 12.5kg Safety-Valved Cylinders.
Flow: Bulk Propane/Butane Bullets → Valve Check & Automated Wash → 24-Head Electronic Carousel → Sniffer Gas Leak & Tare Check → Tamper Shrink Cap & Seal → 60-Cylinder Cage Pallet Truck → Household & Hospitality Agents
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Valve Check & Automated Wash | 2.6 s | 20 min | 96% | 99.1% | 21,000 | 18,200 (1.30 d) | 19,466 |
| 2. 24-Head Electronic Carousel | 3.3 s | 35 min | 93% | 98.4% | 21,000 | 19,600 (1.40 d) | 14,586 |
| 3. Sniffer Gas Leak & Tare Check | 4.1 s | 45 min | 84% | 96.4% | 14,000 | 28,000 (2.00 d) | 10,132 |
| 4. Tamper Shrink Cap & Seal | 2.8 s | 10 min | 96% | 98.8% | 5,600 | 15,400 (1.10 d) | 17,784 |
| 5. 60-Cylinder Cage Pallet Truck | 2.1 s | 10 min | 98% | 99.5% | 3,500 | 11,200 (0.80 d) | 23,960 |
Key figures
- Takt time
- 3.9 s
- Lead time
- 8.10 d
- Value-added time
- 14.9 s
- Process cycle efficiency (PCE)
- 0.003%
- Rolled throughput yield (RTY)
- 92.4%
- Customer demand per day
- 14,000 units
- Line capacity per day
- 10,132 units
- Bottleneck
- Sniffer Gas Leak & Tare Check
Reading the bottleneck
The bottleneck is "Sniffer Gas Leak & Tare Check": it can process 10,132 units per day against a demand of 14,000 units, so it falls short of demand by 27.6%. Once downtime and scrap are counted, its cycle time grows from 4.1 s to 5.1 s, against a takt of 3.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.8 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Oil, Gas, LNG & Refinery Turnarounds: Oil, Gas, LNG & Refinery Turnarounds
- 150kbpd Crude Desalting & Atmospheric Topping
- Base-Load Mixed-Refrigerant LNG Liquefaction Train
- Intelligent MFL Pipeline Inline Integrity Pigging
- Steam Naphtha/Ethane Cracker & Olefins Sep
- Airport Into-Plane Jet-A1 Fuel Farm Filtration
- SBS Polymer-Modified Highway Bitumen Mill
- Hydrocracker 28-Day Refinery Major Turnaround
- 15,000-PSI Subsea / Onshore Christmas Tree Test
- Centrifugal Sour Gas Pipeline Compressor Rebuild
- 300-Bar Fast-Fill CNG / Bio-CNG Fleet Station
- Claus Thermal Sulfur Recovery & Granulation