Claus Thermal Sulfur Recovery & Granulation
Product family: 99.9% Elemental Sulfur Pastilles.
Flow: Refinery Acid H2S Gas → Claus Reaction Furnace Burn → 3-Stage Catalytic Converter → Liquid Sulfur Degassing Pit → Pastille Belt Solidifier → Dust-Free Bulk Rail Silo → Fertilizer Phosphate Acid Plants
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Claus Reaction Furnace Burn | 306 s | 20 min | 96% | 99.1% | 270 | 234 (1.30 d) | 249 |
| 2. 3-Stage Catalytic Converter | 383 s | 35 min | 93% | 98.4% | 270 | 252 (1.40 d) | 190 |
| 3. Liquid Sulfur Degassing Pit | 482 s | 45 min | 84% | 96.4% | 180 | 360 (2.00 d) | 132 |
| 4. Pastille Belt Solidifier | 324 s | 10 min | 96% | 98.8% | 72 | 198 (1.10 d) | 233 |
| 5. Dust-Free Bulk Rail Silo | 243 s | 10 min | 98% | 99.5% | 45 | 144 (0.80 d) | 315 |
Key figures
- Takt time
- 450 s
- Lead time
- 8.12 d
- Value-added time
- 1,738 s
- Process cycle efficiency (PCE)
- 0.26%
- Rolled throughput yield (RTY)
- 92.4%
- Customer demand per day
- 180 tonnes
- Line capacity per day
- 132 tonnes
- Bottleneck
- Liquid Sulfur Degassing Pit
Reading the bottleneck
The bottleneck is "Liquid Sulfur Degassing Pit": it can process 132 tonnes per day against a demand of 180 tonnes, so it falls short of demand by 26.9%. Once downtime and scrap are counted, its cycle time grows from 482 s to 595 s, against a takt of 450 s. The largest loss at this step is equipment downtime (uptime 84%), about 91.8 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Oil, Gas, LNG & Refinery Turnarounds: Oil, Gas, LNG & Refinery Turnarounds
- 150kbpd Crude Desalting & Atmospheric Topping
- Base-Load Mixed-Refrigerant LNG Liquefaction Train
- 2,400-cph LPG Domestic Gas Cylinder Hydro & Fill
- Intelligent MFL Pipeline Inline Integrity Pigging
- Steam Naphtha/Ethane Cracker & Olefins Sep
- Airport Into-Plane Jet-A1 Fuel Farm Filtration
- SBS Polymer-Modified Highway Bitumen Mill
- Hydrocracker 28-Day Refinery Major Turnaround
- 15,000-PSI Subsea / Onshore Christmas Tree Test
- Centrifugal Sour Gas Pipeline Compressor Rebuild
- 300-Bar Fast-Fill CNG / Bio-CNG Fleet Station