Hospital Central Sterile (CSSD) Instrument Loop

Product family: Reprocessed 40-Instrument Trays.

Flow: Operating Theater Soiled → Enzymatic Pre-Soak & Ultrasonic → Washer-Disinfector 93°C Cycle → Optical Loupe Assemble & Count → Steam Autoclave 134°C 18-Min → Cool Check & Case Cart Pull → 8 Hospital Operating Suites

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Hospital Central Sterile (CSSD) Instrument LoopSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Operating Theater Soiled → Enzymatic Pre-Soak & Ultrasonic (127 s) → Washer-Disinfector 93°C Cycle (158 s) → Optical Loupe Assemble & Count (206 s) → Steam Autoclave 134°C 18-Min (139 s) → Cool Check & Case Cart Pull (104 s) → 8 Hospital Operating Suites.SUPPLIEROperatingTheater SoiledI0.80 d1EnzymaticPre-Soak &…C/T 127 sI1.10 d2Washer-Disinfector93°C CycleC/T 158 sI1.50 d3Optical LoupeAssemble & CountC/T 206 sI0.60 d4Steam Autoclave134°C 18-MinC/T 139 sI0.50 d5Cool Check & CaseCart PullC/T 104 sI0.50 dCUSTOMER8 HospitalOperating…280 / crates

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Enzymatic Pre-Soak & Ultrasonic127 s10 min96%97.8%112224 (0.80 d)388
2. Washer-Disinfector 93°C Cycle158 s15 min93%98.2%112308 (1.10 d)299
3. Optical Loupe Assemble & Count206 s25 min85%95.8%140420 (1.50 d)202
4. Steam Autoclave 134°C 18-Min139 s6 min96%99.1%56168 (0.60 d)357
5. Cool Check & Case Cart Pull104 s5 min98%99.5%56140 (0.50 d)492

Key figures

Takt time
193 s
Lead time
5.01 d
Value-added time
734 s
Process cycle efficiency (PCE)
0.27%
Rolled throughput yield (RTY)
90.7%
Customer demand per day
280 crates
Line capacity per day
202 crates
Bottleneck
Optical Loupe Assemble & Count

Reading the bottleneck

The bottleneck is "Optical Loupe Assemble & Count": it can process 202 crates per day against a demand of 280 crates, so it falls short of demand by 28.0%. Once downtime and scrap are counted, its cycle time grows from 206 s to 253 s, against a takt of 193 s. The largest loss at this step is equipment downtime (uptime 85%), about 36.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.