Automated High-Bay Mail-Order Chronic Pharmacy
Product family: 90-Day Chronic Rx Parcels.
Flow: National Wholesale Drugs → E-Script Claim Adjudicate → Robotic Vial Count & Pill Eye → Clinical Pharmacist Screen → Automated Envelope & Cold → Parcel Hub Evening Truck → Home Mail-Order Patients
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. E-Script Claim Adjudicate | 4.2 s | 10 min | 96% | 97.8% | 3,400 | 6,800 (0.80 d) | 11,736 |
| 2. Robotic Vial Count & Pill Eye | 5.2 s | 15 min | 93% | 98.2% | 3,400 | 9,350 (1.10 d) | 9,089 |
| 3. Clinical Pharmacist Screen | 6.8 s | 25 min | 85% | 95.8% | 4,250 | 12,750 (1.50 d) | 6,107 |
| 4. Automated Envelope & Cold | 4.6 s | 6 min | 96% | 99.1% | 1,700 | 5,100 (0.60 d) | 10,796 |
| 5. Parcel Hub Evening Truck | 3.4 s | 5 min | 98% | 99.5% | 1,700 | 4,250 (0.50 d) | 15,057 |
Key figures
- Takt time
- 6.4 s
- Lead time
- 5.00 d
- Value-added time
- 24.2 s
- Process cycle efficiency (PCE)
- 0.009%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 8,500 orders
- Line capacity per day
- 6,107 orders
- Bottleneck
- Clinical Pharmacist Screen
Reading the bottleneck
The bottleneck is "Clinical Pharmacist Screen": it can process 6,107 orders per day against a demand of 8,500 orders, so it falls short of demand by 28.2%. Once downtime and scrap are counted, its cycle time grows from 6.8 s to 8.4 s, against a takt of 6.4 s. The largest loss at this step is equipment downtime (uptime 85%), about 1.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Hospital Pharmacy & CSSD Sterilization: Hospital Pharmacy & CSSD Sterilization
- Hospital ISO-5 Oncology IV Chemo Compounding
- Hospital Central Sterile (CSSD) Instrument Loop
- Neonatal ICU Parenteral Nutrition (TPN) Compounding
- PET/SPECT Radiopharmacy Morning Dose Draw Hub
- Long-Term Care 7-Day Multi-Med Pouches
- Hospital Automated Ward Cabinet Restock
- Outpatient Antibiotic OPAT & Biologic Pump Kit
- EU-GMP Standardized Medical Cannabis Drying & Dose
- Veterinary Flavor-Chew & Equine Rx Compounding
- Global Clinical Trial Drug Depot Temperature Pick
- Multi-Chair Dental Clinic Cassette Sterilization