Multi-Chair Dental Clinic Cassette Sterilization
Product family: Class-B Autoclave Loop.
Flow: Operatory Chairside Suites → Chairside Enzymatic Gel Spray → Thermal Disinfector & Oil Lube → Wrapped Color Cassette Seal → Class-B Vacuum Steam Autoclave → Clean Chair Cupboard Restock → 12 Dental Operatories
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Chairside Enzymatic Gel Spray | 188 s | 10 min | 96% | 97.8% | 38 | 76 (0.80 d) | 127 |
| 2. Thermal Disinfector & Oil Lube | 233 s | 15 min | 93% | 98.2% | 38 | 105 (1.11 d) | 97 |
| 3. Wrapped Color Cassette Seal | 304 s | 25 min | 85% | 95.8% | 48 | 143 (1.51 d) | 64 |
| 4. Class-B Vacuum Steam Autoclave | 205 s | 6 min | 96% | 99.1% | 19 | 57 (0.60 d) | 117 |
| 5. Clean Chair Cupboard Restock | 153 s | 5 min | 98% | 99.5% | 19 | 48 (0.51 d) | 163 |
Key figures
- Takt time
- 284 s
- Lead time
- 5.06 d
- Value-added time
- 1,083 s
- Process cycle efficiency (PCE)
- 0.79%
- Rolled throughput yield (RTY)
- 90.7%
- Customer demand per day
- 95 crates
- Line capacity per day
- 64 crates
- Bottleneck
- Wrapped Color Cassette Seal
Reading the bottleneck
The bottleneck is "Wrapped Color Cassette Seal": it can process 64 crates per day against a demand of 95 crates, so it falls short of demand by 32.2%. Once downtime and scrap are counted, its cycle time grows from 304 s to 373 s, against a takt of 284 s. The largest loss at this step is equipment downtime (uptime 85%), about 53.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Hospital Pharmacy & CSSD Sterilization: Hospital Pharmacy & CSSD Sterilization
- Hospital ISO-5 Oncology IV Chemo Compounding
- Hospital Central Sterile (CSSD) Instrument Loop
- Automated High-Bay Mail-Order Chronic Pharmacy
- Neonatal ICU Parenteral Nutrition (TPN) Compounding
- PET/SPECT Radiopharmacy Morning Dose Draw Hub
- Long-Term Care 7-Day Multi-Med Pouches
- Hospital Automated Ward Cabinet Restock
- Outpatient Antibiotic OPAT & Biologic Pump Kit
- EU-GMP Standardized Medical Cannabis Drying & Dose
- Veterinary Flavor-Chew & Equine Rx Compounding
- Global Clinical Trial Drug Depot Temperature Pick