650-Ton All-Electric Toggle Injection Press

Product family: Servo Molding Machine Line.

Flow: SG Iron Cast Platens → Platen Deep Bore & Ground Face → Chrome Tie-Bar Strain Match → Servo Ballscrew Toggle Mount → Hydraulic Core-Pull & Barrel → Dry Cycle & Clamping Tonnage → Packaging & Auto Molders

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 650-Ton All-Electric Toggle Injection PressSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. SG Iron Cast Platens → Platen Deep Bore & Ground Face (3,672 s) → Chrome Tie-Bar Strain Match (4,590 s) → Servo Ballscrew Toggle Mount (5,940 s) → Hydraulic Core-Pull & Barrel (4,428 s) → Dry Cycle & Clamping Tonnage (3,456 s) → Packaging & Auto Molders.SUPPLIERSG Iron CastPlatensI2.20 d1Platen Deep Bore& Ground FaceC/T 3,672 sI2.40 d2Chrome Tie-BarStrain MatchC/T 4,590 sI2.80 d3Servo BallscrewToggle MountC/T 5,940 sI1.60 d4HydraulicCore-Pull &…C/T 4,428 sI1.00 d5Dry Cycle &Clamping TonnageC/T 3,456 sI1.60 dCUSTOMERPackaging &Auto Molders5 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Platen Deep Bore & Ground Face3,672 s30 min94%98.5%811 (2.20 d)7
2. Chrome Tie-Bar Strain Match4,590 s45 min89%96.4%512 (2.40 d)5
3. Servo Ballscrew Toggle Mount5,940 s90 min83%95.8%514 (2.80 d)3
4. Hydraulic Core-Pull & Barrel4,428 s20 min92%97.4%38 (1.60 d)5
5. Dry Cycle & Clamping Tonnage3,456 s15 min95%98.9%15 (1.00 d)7

Key figures

Takt time
5,400 s
Lead time
12.4 d
Value-added time
22,086 s
Process cycle efficiency (PCE)
6.6%
Rolled throughput yield (RTY)
87.6%
Customer demand per day
5 units
Line capacity per day
3 units
Bottleneck
Servo Ballscrew Toggle Mount

Reading the bottleneck

The bottleneck is "Servo Ballscrew Toggle Mount": it can process 3 units per day against a demand of 5 units, so it falls short of demand by 42.2%. Once downtime and scrap are counted, its cycle time grows from 5,940 s to 7,470 s, against a takt of 5,400 s. The largest loss at this step is equipment downtime (uptime 83%), about 1,217 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.