Cast-Steel Cement Rotary Kiln Riding Ring

Product family: 5.5m Diameter Kiln Tyres.

Flow: Large steel foundries → Arc-Furnace Mold Pour & Cool → Stress-Relief Pit Furnace → 7m Vertical Boring Mill Face → Mag-Particle & UT Scan → Rail Heavy Haul Cradle Load → Global Cement Plants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Cast-Steel Cement Rotary Kiln Riding RingSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Large steel foundries → Arc-Furnace Mold Pour & Cool (6,120 s) → Stress-Relief Pit Furnace (7,650 s) → 7m Vertical Boring Mill Face (9,900 s) → Mag-Particle & UT Scan (7,380 s) → Rail Heavy Haul Cradle Load (5,760 s) → Global Cement Plants.SUPPLIERLarge steelfoundriesI2.00 d1Arc-Furnace MoldPour & CoolC/T 6,120 sI2.33 d2Stress-Relief PitFurnaceC/T 7,650 sI2.67 d37m VerticalBoring Mill FaceC/T 9,900 sI1.67 d4Mag-Particle & UTScanC/T 7,380 sI1.00 d5Rail Heavy HaulCradle LoadC/T 5,760 sI1.67 dCUSTOMERGlobal CementPlants3 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Arc-Furnace Mold Pour & Cool6,120 s30 min94%98.5%56 (2.00 d)4
2. Stress-Relief Pit Furnace7,650 s45 min89%96.4%37 (2.33 d)3
3. 7m Vertical Boring Mill Face9,900 s90 min83%95.8%38 (2.67 d)2
4. Mag-Particle & UT Scan7,380 s20 min92%97.4%25 (1.67 d)3
5. Rail Heavy Haul Cradle Load5,760 s15 min95%98.9%13 (1.00 d)4

Key figures

Takt time
9,000 s
Lead time
12.7 d
Value-added time
36,810 s
Process cycle efficiency (PCE)
10.7%
Rolled throughput yield (RTY)
87.6%
Customer demand per day
3 parts
Line capacity per day
2 parts
Bottleneck
7m Vertical Boring Mill Face

Reading the bottleneck

The bottleneck is "7m Vertical Boring Mill Face": it can process 2 parts per day against a demand of 3 parts, so it falls short of demand by 42.2%. Once downtime and scrap are counted, its cycle time grows from 9,900 s to 12,451 s, against a takt of 9,000 s. The largest loss at this step is equipment downtime (uptime 83%), about 2,028 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.