Cast-Steel Cement Rotary Kiln Riding Ring
Product family: 5.5m Diameter Kiln Tyres.
Flow: Large steel foundries → Arc-Furnace Mold Pour & Cool → Stress-Relief Pit Furnace → 7m Vertical Boring Mill Face → Mag-Particle & UT Scan → Rail Heavy Haul Cradle Load → Global Cement Plants
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Arc-Furnace Mold Pour & Cool | 6,120 s | 30 min | 94% | 98.5% | 5 | 6 (2.00 d) | 4 |
| 2. Stress-Relief Pit Furnace | 7,650 s | 45 min | 89% | 96.4% | 3 | 7 (2.33 d) | 3 |
| 3. 7m Vertical Boring Mill Face | 9,900 s | 90 min | 83% | 95.8% | 3 | 8 (2.67 d) | 2 |
| 4. Mag-Particle & UT Scan | 7,380 s | 20 min | 92% | 97.4% | 2 | 5 (1.67 d) | 3 |
| 5. Rail Heavy Haul Cradle Load | 5,760 s | 15 min | 95% | 98.9% | 1 | 3 (1.00 d) | 4 |
Key figures
- Takt time
- 9,000 s
- Lead time
- 12.7 d
- Value-added time
- 36,810 s
- Process cycle efficiency (PCE)
- 10.7%
- Rolled throughput yield (RTY)
- 87.6%
- Customer demand per day
- 3 parts
- Line capacity per day
- 2 parts
- Bottleneck
- 7m Vertical Boring Mill Face
Reading the bottleneck
The bottleneck is "7m Vertical Boring Mill Face": it can process 2 parts per day against a demand of 3 parts, so it falls short of demand by 42.2%. Once downtime and scrap are counted, its cycle time grows from 9,900 s to 12,451 s, against a takt of 9,000 s. The largest loss at this step is equipment downtime (uptime 83%), about 2,028 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Industrial & Heavy Equipment OEMs: Industrial & Heavy Equipment OEMs
- 5-Axis Turn-Mill Center Machine Bed & Head
- 650-Ton All-Electric Toggle Injection Press
- Self-Propelled Combine Harvester Thresher Line
- 8m³ Spiral-Blade Truck Concrete Mixer Drum
- 25-Ton Double-Girder Overhead Bridge Crane
- 20-Ton Articulated Quarry Wheel Loader
- PE-1200 Heavy Primary Quarry Jaw Crusher Frame
- Forged Hollow 7MW Offshore Wind Main Shaft
- 4-High Cold Steel Rolling Mill Housing Stand
- Cast-Iron Electric Counterbalance Forklift Build
- 150-Ton Constant-Tension Offshore Mooring Winch