Forged Hollow 7MW Offshore Wind Main Shaft

Product family: 52-Ton Flanged Wind Shafts.

Flow: Heavy forge house → Hollow Ingot Open-Die Forge → Rough Deep Boring & Quench → Gantry Lathe & Bearing Grind → UT 100% Volumetric Cert → Protective Oil & Bolt Flange → Wind Nacelle Integrators

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Forged Hollow 7MW Offshore Wind Main ShaftSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Heavy forge house → Hollow Ingot Open-Die Forge (7,344 s) → Rough Deep Boring & Quench (9,180 s) → Gantry Lathe & Bearing Grind (11,880 s) → UT 100% Volumetric Cert (8,856 s) → Protective Oil & Bolt Flange (6,912 s) → Wind Nacelle Integrators.SUPPLIERHeavy forgehouseI2.20 d1Hollow IngotOpen-Die ForgeC/T 7,344 sI2.40 d2Rough Deep Boring& QuenchC/T 9,180 sI2.80 d3Gantry Lathe &Bearing GrindC/T 11,880 sI1.60 d4UT 100%Volumetric CertC/T 8,856 sI1.00 d5Protective Oil &Bolt FlangeC/T 6,912 sI1.60 dCUSTOMERWind NacelleIntegrators5 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Hollow Ingot Open-Die Forge7,344 s30 min94%98.5%811 (2.20 d)7
2. Rough Deep Boring & Quench9,180 s45 min89%96.4%512 (2.40 d)5
3. Gantry Lathe & Bearing Grind11,880 s90 min83%95.8%514 (2.80 d)3
4. UT 100% Volumetric Cert8,856 s20 min92%97.4%38 (1.60 d)5
5. Protective Oil & Bolt Flange6,912 s15 min95%98.9%15 (1.00 d)7

Key figures

Takt time
10,800 s
Lead time
12.4 d
Value-added time
44,172 s
Process cycle efficiency (PCE)
6.6%
Rolled throughput yield (RTY)
87.6%
Customer demand per day
5 parts
Line capacity per day
3 parts
Bottleneck
Gantry Lathe & Bearing Grind

Reading the bottleneck

The bottleneck is "Gantry Lathe & Bearing Grind": it can process 3 parts per day against a demand of 5 parts, so it falls short of demand by 34.9%. Once downtime and scrap are counted, its cycle time grows from 11,880 s to 14,941 s, against a takt of 10,800 s. The largest loss at this step is equipment downtime (uptime 83%), about 2,433 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.