25-Ton Double-Girder Overhead Bridge Crane

Product family: Box-Girder Industrial Cranes.

Flow: S355J2 Heavy Steel → NC Camber-Cut Web Plates → Submerged-Arc Box Closing → End-Truck Wheel Bogie Bore → Wire-Rope Trolley & VFD Panel → 125% Proof Load Hook Deflect → Heavy Steelworks & Foundries

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 25-Ton Double-Girder Overhead Bridge CraneSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. S355J2 Heavy Steel → NC Camber-Cut Web Plates (2,295 s) → Submerged-Arc Box Closing (2,869 s) → End-Truck Wheel Bogie Bore (3,713 s) → Wire-Rope Trolley & VFD Panel (2,768 s) → 125% Proof Load Hook Deflect (2,160 s) → Heavy Steelworks & Foundries.SUPPLIERS355J2 HeavySteelI2.13 d1NC Camber-Cut WebPlatesC/T 2,295 sI2.38 d2Submerged-Arc BoxClosingC/T 2,869 sI2.75 d3End-Truck WheelBogie BoreC/T 3,713 sI1.50 d4Wire-Rope Trolley& VFD PanelC/T 2,768 sI0.88 d5125% Proof LoadHook DeflectC/T 2,160 sI1.50 dCUSTOMERHeavySteelworks &…8 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. NC Camber-Cut Web Plates2,295 s30 min94%98.5%1217 (2.13 d)10
2. Submerged-Arc Box Closing2,869 s45 min89%96.4%819 (2.38 d)7
3. End-Truck Wheel Bogie Bore3,713 s90 min83%95.8%822 (2.75 d)5
4. Wire-Rope Trolley & VFD Panel2,768 s20 min92%97.4%412 (1.50 d)8
5. 125% Proof Load Hook Deflect2,160 s15 min95%98.9%27 (0.88 d)10

Key figures

Takt time
3,375 s
Lead time
11.6 d
Value-added time
13,805 s
Process cycle efficiency (PCE)
4.4%
Rolled throughput yield (RTY)
87.6%
Customer demand per day
8 units
Line capacity per day
5 units
Bottleneck
End-Truck Wheel Bogie Bore

Reading the bottleneck

The bottleneck is "End-Truck Wheel Bogie Bore": it can process 5 units per day against a demand of 8 units, so it falls short of demand by 42.2%. Once downtime and scrap are counted, its cycle time grows from 3,713 s to 4,670 s, against a takt of 3,375 s. The largest loss at this step is equipment downtime (uptime 83%), about 760 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.