Cast-Iron Electric Counterbalance Forklift Build

Product family: 3-Ton Lithium Fleet Forklifts.

Flow: LFP Battery & Traction Drive → Chassis & Counterweight Fit → AC Drive Axle & Pump Motor → Triplex Mast & Tilt Ram Mate → LFP Pack Drop & Harness Plug → Tilt Stability & Lift Cert → Logistics Warehouses

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Cast-Iron Electric Counterbalance Forklift BuildSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. LFP Battery & Traction Drive → Chassis & Counterweight Fit (565 s) → AC Drive Axle & Pump Motor (706 s) → Triplex Mast & Tilt Ram Mate (914 s) → LFP Pack Drop & Harness Plug (681 s) → Tilt Stability & Lift Cert (532 s) → Logistics Warehouses.SUPPLIERLFP Battery &Traction DriveI2.11 d1Chassis &Counterweight FitC/T 565 sI2.40 d2AC Drive Axle &Pump MotorC/T 706 sI2.80 d3Triplex Mast &Tilt Ram MateC/T 914 sI1.51 d4LFP Pack Drop &Harness PlugC/T 681 sI0.91 d5Tilt Stability &Lift CertC/T 532 sI1.51 dCUSTOMERLogisticsWarehouses65 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Chassis & Counterweight Fit565 s30 min94%98.5%98137 (2.11 d)87
2. AC Drive Axle & Pump Motor706 s45 min89%96.4%65156 (2.40 d)62
3. Triplex Mast & Tilt Ram Mate914 s90 min83%95.8%65182 (2.80 d)42
4. LFP Pack Drop & Harness Plug681 s20 min92%97.4%3398 (1.51 d)68
5. Tilt Stability & Lift Cert532 s15 min95%98.9%1659 (0.91 d)89

Key figures

Takt time
831 s
Lead time
11.3 d
Value-added time
3,398 s
Process cycle efficiency (PCE)
0.56%
Rolled throughput yield (RTY)
87.6%
Customer demand per day
65 units
Line capacity per day
42 units
Bottleneck
Triplex Mast & Tilt Ram Mate

Reading the bottleneck

The bottleneck is "Triplex Mast & Tilt Ram Mate": it can process 42 units per day against a demand of 65 units, so it falls short of demand by 35.0%. Once downtime and scrap are counted, its cycle time grows from 914 s to 1,149 s, against a takt of 831 s. The largest loss at this step is equipment downtime (uptime 83%), about 187 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.