20-Ton Articulated Quarry Wheel Loader
Product family: High-Breakout Front Loaders.
Flow: Axle & engine supplier → Front/Rear Articulated Chassis → Z-Bar Linkage Bore & Paint → Axle, Trans & Engine Drop → Cab HVAC & Joystick Calib → 3-Hour Dig Cycle Endurance → Mining & Quarry Dealers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Front/Rear Articulated Chassis | 2,623 s | 30 min | 94% | 98.5% | 21 | 29 (2.07 d) | 19 |
| 2. Z-Bar Linkage Bore & Paint | 3,279 s | 45 min | 89% | 96.4% | 14 | 34 (2.43 d) | 13 |
| 3. Axle, Trans & Engine Drop | 4,243 s | 90 min | 83% | 95.8% | 14 | 39 (2.79 d) | 9 |
| 4. Cab HVAC & Joystick Calib | 3,163 s | 20 min | 92% | 97.4% | 7 | 21 (1.50 d) | 15 |
| 5. 3-Hour Dig Cycle Endurance | 2,469 s | 15 min | 95% | 98.9% | 4 | 13 (0.93 d) | 19 |
Key figures
- Takt time
- 3,857 s
- Lead time
- 11.5 d
- Value-added time
- 15,777 s
- Process cycle efficiency (PCE)
- 2.5%
- Rolled throughput yield (RTY)
- 87.6%
- Customer demand per day
- 14 units
- Line capacity per day
- 9 units
- Bottleneck
- Axle, Trans & Engine Drop
Reading the bottleneck
The bottleneck is "Axle, Trans & Engine Drop": it can process 9 units per day against a demand of 14 units, so it falls short of demand by 34.9%. Once downtime and scrap are counted, its cycle time grows from 4,243 s to 5,336 s, against a takt of 3,857 s. The largest loss at this step is equipment downtime (uptime 83%), about 869 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Industrial & Heavy Equipment OEMs: Industrial & Heavy Equipment OEMs
- 5-Axis Turn-Mill Center Machine Bed & Head
- 650-Ton All-Electric Toggle Injection Press
- Self-Propelled Combine Harvester Thresher Line
- 8m³ Spiral-Blade Truck Concrete Mixer Drum
- 25-Ton Double-Girder Overhead Bridge Crane
- PE-1200 Heavy Primary Quarry Jaw Crusher Frame
- Forged Hollow 7MW Offshore Wind Main Shaft
- 4-High Cold Steel Rolling Mill Housing Stand
- Cast-Steel Cement Rotary Kiln Riding Ring
- Cast-Iron Electric Counterbalance Forklift Build
- 150-Ton Constant-Tension Offshore Mooring Winch