20-Ton Articulated Quarry Wheel Loader

Product family: High-Breakout Front Loaders.

Flow: Axle & engine supplier → Front/Rear Articulated Chassis → Z-Bar Linkage Bore & Paint → Axle, Trans & Engine Drop → Cab HVAC & Joystick Calib → 3-Hour Dig Cycle Endurance → Mining & Quarry Dealers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 20-Ton Articulated Quarry Wheel LoaderSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Axle & engine supplier → Front/Rear Articulated Chassis (2,623 s) → Z-Bar Linkage Bore & Paint (3,279 s) → Axle, Trans & Engine Drop (4,243 s) → Cab HVAC & Joystick Calib (3,163 s) → 3-Hour Dig Cycle Endurance (2,469 s) → Mining & Quarry Dealers.SUPPLIERAxle & enginesupplierI2.07 d1Front/RearArticulated…C/T 2,623 sI2.43 d2Z-Bar LinkageBore & PaintC/T 3,279 sI2.79 d3Axle, Trans &Engine DropC/T 4,243 sI1.50 d4Cab HVAC &Joystick CalibC/T 3,163 sI0.93 d53-Hour Dig CycleEnduranceC/T 2,469 sI1.50 dCUSTOMERMining & QuarryDealers14 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Front/Rear Articulated Chassis2,623 s30 min94%98.5%2129 (2.07 d)19
2. Z-Bar Linkage Bore & Paint3,279 s45 min89%96.4%1434 (2.43 d)13
3. Axle, Trans & Engine Drop4,243 s90 min83%95.8%1439 (2.79 d)9
4. Cab HVAC & Joystick Calib3,163 s20 min92%97.4%721 (1.50 d)15
5. 3-Hour Dig Cycle Endurance2,469 s15 min95%98.9%413 (0.93 d)19

Key figures

Takt time
3,857 s
Lead time
11.5 d
Value-added time
15,777 s
Process cycle efficiency (PCE)
2.5%
Rolled throughput yield (RTY)
87.6%
Customer demand per day
14 units
Line capacity per day
9 units
Bottleneck
Axle, Trans & Engine Drop

Reading the bottleneck

The bottleneck is "Axle, Trans & Engine Drop": it can process 9 units per day against a demand of 14 units, so it falls short of demand by 34.9%. Once downtime and scrap are counted, its cycle time grows from 4,243 s to 5,336 s, against a takt of 3,857 s. The largest loss at this step is equipment downtime (uptime 83%), about 869 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Industrial & Heavy Equipment OEMs: Industrial & Heavy Equipment OEMs