Self-Propelled Combine Harvester Thresher Line

Product family: Class-9 Grain Harvesters.

Flow: Harvester steel supplier → Chassis Frame Robot Weld → E-Coat & Signature Paint → Rotary Rotor & Engine Drop → Cab, Header Lift & GPS Wire → Full-Grain Simulation Run → Agricultural Cooperatives

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Self-Propelled Combine Harvester Thresher LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Harvester steel supplier → Chassis Frame Robot Weld (3,672 s) → E-Coat & Signature Paint (4,590 s) → Rotary Rotor & Engine Drop (5,940 s) → Cab, Header Lift & GPS Wire (4,428 s) → Full-Grain Simulation Run (3,456 s) → Agricultural Cooperatives.SUPPLIERHarvester steelsupplierI2.10 d1Chassis FrameRobot WeldC/T 3,672 sI2.40 d2E-Coat &Signature PaintC/T 4,590 sI2.80 d3Rotary Rotor &Engine DropC/T 5,940 sI1.50 d4Cab, Header Lift& GPS WireC/T 4,428 sI0.90 d5Full-GrainSimulation RunC/T 3,456 sI1.50 dCUSTOMERAgriculturalCooperatives10 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Chassis Frame Robot Weld3,672 s30 min94%98.5%1521 (2.10 d)13
2. E-Coat & Signature Paint4,590 s45 min89%96.4%1024 (2.40 d)10
3. Rotary Rotor & Engine Drop5,940 s90 min83%95.8%1028 (2.80 d)7
4. Cab, Header Lift & GPS Wire4,428 s20 min92%97.4%515 (1.50 d)10
5. Full-Grain Simulation Run3,456 s15 min95%98.9%39 (0.90 d)14

Key figures

Takt time
5,400 s
Lead time
11.6 d
Value-added time
22,086 s
Process cycle efficiency (PCE)
3.5%
Rolled throughput yield (RTY)
87.6%
Customer demand per day
10 units
Line capacity per day
7 units
Bottleneck
Rotary Rotor & Engine Drop

Reading the bottleneck

The bottleneck is "Rotary Rotor & Engine Drop": it can process 7 units per day against a demand of 10 units, so it falls short of demand by 34.9%. Once downtime and scrap are counted, its cycle time grows from 5,940 s to 7,470 s, against a takt of 5,400 s. The largest loss at this step is equipment downtime (uptime 83%), about 1,217 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family