PE-1200 Heavy Primary Quarry Jaw Crusher Frame

Product family: Manganese Jaw Crushing Units.

Flow: 18% Mn Steel Foundry → Side-Plate Bolt & Weld Box → Giant CNC Eccentric Bearing Bore → 18% Mn Pitman Jaw Casting Fit → Flywheel Taper Shrink Mount → No-Load Vibration & Bearing Run → Mine Aggregate Operators

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: PE-1200 Heavy Primary Quarry Jaw Crusher FrameSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. 18% Mn Steel Foundry → Side-Plate Bolt & Weld Box (3,672 s) → Giant CNC Eccentric Bearing Bore (4,590 s) → 18% Mn Pitman Jaw Casting Fit (5,940 s) → Flywheel Taper Shrink Mount (4,428 s) → No-Load Vibration & Bearing Run (3,456 s) → Mine Aggregate Operators.SUPPLIER18% Mn SteelFoundryI2.20 d1Side-Plate Bolt &Weld BoxC/T 3,672 sI2.40 d2Giant CNCEccentric Bearin…C/T 4,590 sI2.80 d318% Mn Pitman JawCasting FitC/T 5,940 sI1.60 d4Flywheel TaperShrink MountC/T 4,428 sI1.00 d5No-Load Vibration& Bearing RunC/T 3,456 sI1.60 dCUSTOMERMine AggregateOperators5 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Side-Plate Bolt & Weld Box3,672 s30 min94%98.5%811 (2.20 d)7
2. Giant CNC Eccentric Bearing Bore4,590 s45 min89%96.4%512 (2.40 d)5
3. 18% Mn Pitman Jaw Casting Fit5,940 s90 min83%95.8%514 (2.80 d)3
4. Flywheel Taper Shrink Mount4,428 s20 min92%97.4%38 (1.60 d)5
5. No-Load Vibration & Bearing Run3,456 s15 min95%98.9%15 (1.00 d)7

Key figures

Takt time
5,400 s
Lead time
12.4 d
Value-added time
22,086 s
Process cycle efficiency (PCE)
6.6%
Rolled throughput yield (RTY)
87.6%
Customer demand per day
5 units
Line capacity per day
3 units
Bottleneck
18% Mn Pitman Jaw Casting Fit

Reading the bottleneck

The bottleneck is "18% Mn Pitman Jaw Casting Fit": it can process 3 units per day against a demand of 5 units, so it falls short of demand by 42.2%. Once downtime and scrap are counted, its cycle time grows from 5,940 s to 7,470 s, against a takt of 5,400 s. The largest loss at this step is equipment downtime (uptime 83%), about 1,217 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.