Multistage Stainless Deep-Well Submersible
Product family: 316L Water Lift Turbines.
Flow: Stainless steel mill → Impeller Spot-Weld & Bal → Stainless Diffuser Deep-Draw → Water-Lubed Ceramic Bearing → Canned Submersible Stator → 180m Head Curve Hydro Test → Municipal Water Utilities
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Impeller Spot-Weld & Bal | 274 s | 25 min | 95% | 98.8% | 130 | 208 (1.60 d) | 180 |
| 2. Stainless Diffuser Deep-Draw | 349 s | 38 min | 91% | 97.6% | 104 | 221 (1.70 d) | 130 |
| 3. Water-Lubed Ceramic Bearing | 444 s | 45 min | 84% | 95.0% | 130 | 286 (2.20 d) | 92 |
| 4. Canned Submersible Stator | 324 s | 15 min | 94% | 98.2% | 52 | 130 (1.00 d) | 147 |
| 5. 180m Head Curve Hydro Test | 258 s | 10 min | 96% | 99.1% | 26 | 91 (0.70 d) | 188 |
Key figures
- Takt time
- 415 s
- Lead time
- 8.73 d
- Value-added time
- 1,649 s
- Process cycle efficiency (PCE)
- 0.35%
- Rolled throughput yield (RTY)
- 89.1%
- Customer demand per day
- 130 units
- Line capacity per day
- 92 units
- Bottleneck
- Water-Lubed Ceramic Bearing
Reading the bottleneck
The bottleneck is "Water-Lubed Ceramic Bearing": it can process 92 units per day against a demand of 130 units, so it falls short of demand by 29.1%. Once downtime and scrap are counted, its cycle time grows from 444 s to 556 s, against a takt of 415 s. The largest loss at this step is equipment downtime (uptime 84%), about 84.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Hydraulics, Pumps & Valves: Hydraulics, Pumps & Valves
- Swashplate Axial Piston Hydraulic Pump 280cc
- Double-Acting Telescopic Chrome Cylinder
- Proportional Electro-Hydraulic Valve Bank
- SAE 100R15 Spiral Hydraulic Hose Assembly
- Oil-Injected Rotary Screw Air-End 90kW
- High-Chrome Abrasive Mining Slurry Pump
- Right-Angle Helical-Bevel Conveyor Drive
- 6MW Offshore Wind Planetary Multiplier
- ISO 15552 Anodized Pneumatic Cylinder Cell
- API-600 Forged Carbon Steel Steam Globe Valve
- Dry Claw Industrial Vacuum Pump Cell