Right-Angle Helical-Bevel Conveyor Drive

Product family: IP66 Modular Industrial Drives.

Flow: 20MnCr5 Alloy Steel → Bevel Gear Cut → Gas Carburize & Quench → Gear Tooth Grind → Case Seal & Synthetic Fill → Full-Torque NVH Run Bench → Port & Mine Conveyors

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Right-Angle Helical-Bevel Conveyor DriveSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. 20MnCr5 Alloy Steel → Bevel Gear Cut (188 s) → Gas Carburize & Quench (239 s) → Gear Tooth Grind (304 s) → Case Seal & Synthetic Fill (222 s) → Full-Torque NVH Run Bench (176 s) → Port & Mine Conveyors.SUPPLIER20MnCr5 AlloySteelI1.60 d1Bevel Gear CutC/T 188 sI1.70 d2Gas Carburize &QuenchC/T 239 sI2.20 d3Gear Tooth GrindC/T 304 sI1.00 d4Case Seal &Synthetic FillC/T 222 sI0.70 d5Full-Torque NVHRun BenchC/T 176 sI1.50 dCUSTOMERPort & MineConveyors190 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Bevel Gear Cut188 s25 min95%98.8%190304 (1.60 d)262
2. Gas Carburize & Quench239 s38 min91%97.6%152323 (1.70 d)190
3. Gear Tooth Grind304 s45 min84%95.0%190418 (2.20 d)135
4. Case Seal & Synthetic Fill222 s15 min94%98.2%76190 (1.00 d)215
5. Full-Torque NVH Run Bench176 s10 min96%99.1%38133 (0.70 d)276

Key figures

Takt time
284 s
Lead time
8.72 d
Value-added time
1,129 s
Process cycle efficiency (PCE)
0.24%
Rolled throughput yield (RTY)
89.1%
Customer demand per day
190 units
Line capacity per day
135 units
Bottleneck
Gear Tooth Grind

Reading the bottleneck

The bottleneck is "Gear Tooth Grind": it can process 135 units per day against a demand of 190 units, so it falls short of demand by 29.1%. Once downtime and scrap are counted, its cycle time grows from 304 s to 381 s, against a takt of 284 s. The largest loss at this step is equipment downtime (uptime 84%), about 57.9 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.