Dry Claw Industrial Vacuum Pump Cell
Product family: Oil-Free Chemical Vacuum Pumps.
Flow: Spheroidal Cast Iron → CNC Figure-8 Pump Stator → 5-Axis Claw Rotor Profile → PTFE Anti-Corrosion Coat → Timing Gear Phase Sync → Ultimate Vacuum Leak Bench → Pharma & Packaging Lines
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. CNC Figure-8 Pump Stator | 594 s | 25 min | 95% | 98.8% | 60 | 96 (1.60 d) | 83 |
| 2. 5-Axis Claw Rotor Profile | 756 s | 38 min | 91% | 97.6% | 48 | 102 (1.70 d) | 60 |
| 3. PTFE Anti-Corrosion Coat | 963 s | 45 min | 84% | 95.0% | 60 | 132 (2.20 d) | 43 |
| 4. Timing Gear Phase Sync | 702 s | 15 min | 94% | 98.2% | 24 | 60 (1.00 d) | 68 |
| 5. Ultimate Vacuum Leak Bench | 558 s | 10 min | 96% | 99.1% | 12 | 42 (0.70 d) | 87 |
Key figures
- Takt time
- 900 s
- Lead time
- 8.77 d
- Value-added time
- 3,573 s
- Process cycle efficiency (PCE)
- 0.75%
- Rolled throughput yield (RTY)
- 89.1%
- Customer demand per day
- 60 units
- Line capacity per day
- 43 units
- Bottleneck
- PTFE Anti-Corrosion Coat
Reading the bottleneck
The bottleneck is "PTFE Anti-Corrosion Coat": it can process 43 units per day against a demand of 60 units, so it falls short of demand by 29.1%. Once downtime and scrap are counted, its cycle time grows from 963 s to 1,207 s, against a takt of 900 s. The largest loss at this step is equipment downtime (uptime 84%), about 183 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Hydraulics, Pumps & Valves: Hydraulics, Pumps & Valves
- Swashplate Axial Piston Hydraulic Pump 280cc
- Double-Acting Telescopic Chrome Cylinder
- Proportional Electro-Hydraulic Valve Bank
- SAE 100R15 Spiral Hydraulic Hose Assembly
- Oil-Injected Rotary Screw Air-End 90kW
- High-Chrome Abrasive Mining Slurry Pump
- Right-Angle Helical-Bevel Conveyor Drive
- Multistage Stainless Deep-Well Submersible
- 6MW Offshore Wind Planetary Multiplier
- ISO 15552 Anodized Pneumatic Cylinder Cell
- API-600 Forged Carbon Steel Steam Globe Valve