ISO 15552 Anodized Pneumatic Cylinder Cell

Product family: Magnetic Double-Acting Rams.

Flow: Aluminum extrusion house → Extruded Barrel Cut & Anodize → Piston Rod Thread & Burnish → Magnetic Ring & Seal Press → Tie-Rod Torque & Cushion Set → End-Position Reed Switch QC → Factory Automation Distributors

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: ISO 15552 Anodized Pneumatic Cylinder CellSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Aluminum extrusion house → Extruded Barrel Cut & Anodize (16.2 s) → Piston Rod Thread & Burnish (20.6 s) → Magnetic Ring & Seal Press (26.3 s) → Tie-Rod Torque & Cushion Set (19.1 s) → End-Position Reed Switch QC (15.2 s) → Factory Automation Distributors.SUPPLIERAluminumextrusion houseI1.60 d1Extruded BarrelCut & AnodizeC/T 16.2 sI1.70 d2Piston Rod Thread& BurnishC/T 20.6 sI2.20 d3Magnetic Ring &Seal PressC/T 26.3 sI1.00 d4Tie-Rod Torque &Cushion SetC/T 19.1 sI0.70 d5End-Position ReedSwitch QCC/T 15.2 sI1.50 dCUSTOMERFactoryAutomation…2,200 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Extruded Barrel Cut & Anodize16.2 s25 min95%98.8%2,2003,520 (1.60 d)3,042
2. Piston Rod Thread & Burnish20.6 s38 min91%97.6%1,7603,740 (1.70 d)2,205
3. Magnetic Ring & Seal Press26.3 s45 min84%95.0%2,2004,840 (2.20 d)1,557
4. Tie-Rod Torque & Cushion Set19.1 s15 min94%98.2%8802,200 (1.00 d)2,501
5. End-Position Reed Switch QC15.2 s10 min96%99.1%4401,540 (0.70 d)3,192

Key figures

Takt time
24.5 s
Lead time
8.70 d
Value-added time
97.4 s
Process cycle efficiency (PCE)
0.021%
Rolled throughput yield (RTY)
89.1%
Customer demand per day
2,200 units
Line capacity per day
1,557 units
Bottleneck
Magnetic Ring & Seal Press

Reading the bottleneck

The bottleneck is "Magnetic Ring & Seal Press": it can process 1,557 units per day against a demand of 2,200 units, so it falls short of demand by 29.2%. Once downtime and scrap are counted, its cycle time grows from 26.3 s to 33.0 s, against a takt of 24.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 5.0 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Hydraulics, Pumps & Valves: Hydraulics, Pumps & Valves