Oil-Injected Rotary Screw Air-End 90kW
Product family: Industrial Compressed Air Ends.
Flow: G25 Grey Cast Iron → Helical Rotor CNC Mill → Rotor Profile Form Grinding → Housing Tri-Lobe Bore CNC → Angular Bearing Shim Stack → 13-Bar Efficiency Run-In → Plant Air Integrators
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Helical Rotor CNC Mill | 792 s | 25 min | 95% | 98.8% | 45 | 72 (1.60 d) | 62 |
| 2. Rotor Profile Form Grinding | 1,008 s | 38 min | 91% | 97.6% | 36 | 77 (1.71 d) | 45 |
| 3. Housing Tri-Lobe Bore CNC | 1,284 s | 45 min | 84% | 95.0% | 45 | 99 (2.20 d) | 32 |
| 4. Angular Bearing Shim Stack | 936 s | 15 min | 94% | 98.2% | 18 | 45 (1.00 d) | 51 |
| 5. 13-Bar Efficiency Run-In | 744 s | 10 min | 96% | 99.1% | 9 | 31 (0.69 d) | 65 |
Key figures
- Takt time
- 1,200 s
- Lead time
- 8.80 d
- Value-added time
- 4,764 s
- Process cycle efficiency (PCE)
- 1.0%
- Rolled throughput yield (RTY)
- 89.1%
- Customer demand per day
- 45 units
- Line capacity per day
- 32 units
- Bottleneck
- Housing Tri-Lobe Bore CNC
Reading the bottleneck
The bottleneck is "Housing Tri-Lobe Bore CNC": it can process 32 units per day against a demand of 45 units, so it falls short of demand by 29.1%. Once downtime and scrap are counted, its cycle time grows from 1,284 s to 1,609 s, against a takt of 1,200 s. The largest loss at this step is equipment downtime (uptime 84%), about 245 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Hydraulics, Pumps & Valves: Hydraulics, Pumps & Valves
- Swashplate Axial Piston Hydraulic Pump 280cc
- Double-Acting Telescopic Chrome Cylinder
- Proportional Electro-Hydraulic Valve Bank
- SAE 100R15 Spiral Hydraulic Hose Assembly
- High-Chrome Abrasive Mining Slurry Pump
- Right-Angle Helical-Bevel Conveyor Drive
- Multistage Stainless Deep-Well Submersible
- 6MW Offshore Wind Planetary Multiplier
- ISO 15552 Anodized Pneumatic Cylinder Cell
- API-600 Forged Carbon Steel Steam Globe Valve
- Dry Claw Industrial Vacuum Pump Cell