6MW Offshore Wind Planetary Multiplier

Product family: 3-Stage Helical Wind Drives.

Flow: Forged ring-gear supplier → 2.5m Ring Gear Hob & Grind → Deep-Case Carburize & Anneal → Planetary Carrier Bore Align → Oil Jet & Sensor Wiring → Back-to-Back 6MW Full Load → Offshore Nacelle OEMs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 6MW Offshore Wind Planetary MultiplierSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Forged ring-gear supplier → 2.5m Ring Gear Hob & Grind (8,910 s) → Deep-Case Carburize & Anneal (11,340 s) → Planetary Carrier Bore Align (14,445 s) → Oil Jet & Sensor Wiring (10,530 s) → Back-to-Back 6MW Full Load (8,370 s) → Offshore Nacelle OEMs.SUPPLIERForgedring-gearsupplierI1.50 d12.5m Ring GearHob & GrindC/T 8,910 sI1.75 d2Deep-CaseCarburize &…C/T 11,340 sI2.25 d3Planetary CarrierBore AlignC/T 14,445 sI1.00 d4Oil Jet & SensorWiringC/T 10,530 sI0.75 d5Back-to-Back 6MWFull LoadC/T 8,370 sI1.50 dCUSTOMEROffshoreNacelle OEMs4 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 2.5m Ring Gear Hob & Grind8,910 s25 min95%98.8%46 (1.50 d)6
2. Deep-Case Carburize & Anneal11,340 s38 min91%97.6%37 (1.75 d)4
3. Planetary Carrier Bore Align14,445 s45 min84%95.0%49 (2.25 d)3
4. Oil Jet & Sensor Wiring10,530 s15 min94%98.2%24 (1.00 d)5
5. Back-to-Back 6MW Full Load8,370 s10 min96%99.1%13 (0.75 d)6

Key figures

Takt time
13,500 s
Lead time
9.74 d
Value-added time
53,595 s
Process cycle efficiency (PCE)
10.2%
Rolled throughput yield (RTY)
89.1%
Customer demand per day
4 units
Line capacity per day
3 units
Bottleneck
Planetary Carrier Bore Align

Reading the bottleneck

The bottleneck is "Planetary Carrier Bore Align": it can process 3 units per day against a demand of 4 units, so it falls short of demand by 29.1%. Once downtime and scrap are counted, its cycle time grows from 14,445 s to 18,102 s, against a takt of 13,500 s. The largest loss at this step is equipment downtime (uptime 84%), about 2,751 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.