API-600 Forged Carbon Steel Steam Globe Valve
Product family: High-Temp Power Plant Valves.
Flow: Forged A105 Steel → Body Flange Face & Thread → Cobalt-Alloy Hardface Weld Seat → Precision Lap Plug & Seat → Bonnet Graphite Packing Torque → API-598 Shell & Seat Hydro → Power & Petrochem Plants
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Body Flange Face & Thread | 419 s | 25 min | 95% | 98.8% | 85 | 136 (1.60 d) | 118 |
| 2. Cobalt-Alloy Hardface Weld Seat | 534 s | 38 min | 91% | 97.6% | 68 | 145 (1.71 d) | 85 |
| 3. Precision Lap Plug & Seat | 680 s | 45 min | 84% | 95.0% | 85 | 187 (2.20 d) | 60 |
| 4. Bonnet Graphite Packing Torque | 496 s | 15 min | 94% | 98.2% | 34 | 85 (1.00 d) | 96 |
| 5. API-598 Shell & Seat Hydro | 394 s | 10 min | 96% | 99.1% | 17 | 59 (0.69 d) | 123 |
Key figures
- Takt time
- 635 s
- Lead time
- 8.75 d
- Value-added time
- 2,523 s
- Process cycle efficiency (PCE)
- 0.53%
- Rolled throughput yield (RTY)
- 89.1%
- Customer demand per day
- 85 units
- Line capacity per day
- 60 units
- Bottleneck
- Precision Lap Plug & Seat
Reading the bottleneck
The bottleneck is "Precision Lap Plug & Seat": it can process 60 units per day against a demand of 85 units, so it falls short of demand by 29.2%. Once downtime and scrap are counted, its cycle time grows from 680 s to 852 s, against a takt of 635 s. The largest loss at this step is equipment downtime (uptime 84%), about 130 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Hydraulics, Pumps & Valves: Hydraulics, Pumps & Valves
- Swashplate Axial Piston Hydraulic Pump 280cc
- Double-Acting Telescopic Chrome Cylinder
- Proportional Electro-Hydraulic Valve Bank
- SAE 100R15 Spiral Hydraulic Hose Assembly
- Oil-Injected Rotary Screw Air-End 90kW
- High-Chrome Abrasive Mining Slurry Pump
- Right-Angle Helical-Bevel Conveyor Drive
- Multistage Stainless Deep-Well Submersible
- 6MW Offshore Wind Planetary Multiplier
- ISO 15552 Anodized Pneumatic Cylinder Cell
- Dry Claw Industrial Vacuum Pump Cell