SAE 100R15 Spiral Hydraulic Hose Assembly

Product family: 420-Bar Multi-Spiral Hoses.

Flow: Hose & coupling supplier → Orbital Cut & Internal Skive → Ultrasonic Foam Clean Blast → Laser Marker Crimp Depth Set → 840-Bar Impulse Burst Audit → Barcoded Cap & Kit Bagging → OEM Hose Kitting Lines

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: SAE 100R15 Spiral Hydraulic Hose AssemblySupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Hose & coupling supplier → Orbital Cut & Internal Skive (25.5 s) → Ultrasonic Foam Clean Blast (32.4 s) → Laser Marker Crimp Depth Set (41.0 s) → 840-Bar Impulse Burst Audit (30.1 s) → Barcoded Cap & Kit Bagging (23.9 s) → OEM Hose Kitting Lines.SUPPLIERHose & couplingsupplierI1.60 d1Orbital Cut &Internal SkiveC/T 25.5 sI1.70 d2Ultrasonic FoamClean BlastC/T 32.4 sI2.20 d3Laser MarkerCrimp Depth SetC/T 41.0 sI1.00 d4840-Bar ImpulseBurst AuditC/T 30.1 sI0.70 d5Barcoded Cap &Kit BaggingC/T 23.9 sI1.50 dCUSTOMEROEM HoseKitting Lines1,400 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Orbital Cut & Internal Skive25.5 s25 min95%98.8%1,4002,240 (1.60 d)1,932
2. Ultrasonic Foam Clean Blast32.4 s38 min91%97.6%1,1202,380 (1.70 d)1,402
3. Laser Marker Crimp Depth Set41.0 s45 min84%95.0%1,4003,080 (2.20 d)998
4. 840-Bar Impulse Burst Audit30.1 s15 min94%98.2%5601,400 (1.00 d)1,587
5. Barcoded Cap & Kit Bagging23.9 s10 min96%99.1%280980 (0.70 d)2,030

Key figures

Takt time
38.6 s
Lead time
8.70 d
Value-added time
153 s
Process cycle efficiency (PCE)
0.033%
Rolled throughput yield (RTY)
89.1%
Customer demand per day
1,400 units
Line capacity per day
998 units
Bottleneck
Laser Marker Crimp Depth Set

Reading the bottleneck

The bottleneck is "Laser Marker Crimp Depth Set": it can process 998 units per day against a demand of 1,400 units, so it falls short of demand by 28.7%. Once downtime and scrap are counted, its cycle time grows from 41.0 s to 51.4 s, against a takt of 38.6 s. The largest loss at this step is equipment downtime (uptime 84%), about 7.8 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.