Circular Second-Hand Apparel Steam, Photo & List

Product family: Single-SKU Resale Fulfillment.

Flow: Consumer Closet Cleanouts → NFC Tag & Brand Auth Verify → Spot Stain & Ozone Sanitize → 360° AI Ghost Mannequin Photo → Poly-Free Paper Bag Bin Put → Single-Item Pick & Ship → Resale Online Platforms

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Circular Second-Hand Apparel Steam, Photo & ListSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Consumer Closet Cleanouts → NFC Tag & Brand Auth Verify (16.7 s) → Spot Stain & Ozone Sanitize (19.6 s) → 360° AI Ghost Mannequin Photo (26.5 s) → Poly-Free Paper Bag Bin Put (18.2 s) → Single-Item Pick & Ship (13.7 s) → Resale Online Platforms.SUPPLIERConsumer ClosetCleanoutsI1.60 d1NFC Tag & BrandAuth VerifyC/T 16.7 sI1.80 d2Spot Stain &Ozone SanitizeC/T 19.6 sI2.40 d3360° AI GhostMannequin PhotoC/T 26.5 sI0.90 d4Poly-Free PaperBag Bin PutC/T 18.2 sI0.80 d5Single-Item Pick& ShipC/T 13.7 sI1.40 dCUSTOMERResale OnlinePlatforms2,200 / garments

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. NFC Tag & Brand Auth Verify16.7 s12 min95%98.1%1,1003,520 (1.60 d)2,933
2. Spot Stain & Ozone Sanitize19.6 s15 min92%96.4%8803,960 (1.80 d)2,342
3. 360° AI Ghost Mannequin Photo26.5 s20 min84%92.5%1,1005,280 (2.40 d)1,513
4. Poly-Free Paper Bag Bin Put18.2 s8 min95%98.2%5501,980 (0.90 d)2,670
5. Single-Item Pick & Ship13.7 s8 min97%99.4%5501,760 (0.80 d)3,665

Key figures

Takt time
24.5 s
Lead time
8.90 d
Value-added time
94.7 s
Process cycle efficiency (PCE)
0.020%
Rolled throughput yield (RTY)
85.4%
Customer demand per day
2,200 garments
Line capacity per day
1,513 garments
Bottleneck
360° AI Ghost Mannequin Photo

Reading the bottleneck

The bottleneck is "360° AI Ghost Mannequin Photo": it can process 1,513 garments per day against a demand of 2,200 garments, so it falls short of demand by 31.2%. Once downtime and scrap are counted, its cycle time grows from 26.5 s to 34.1 s, against a takt of 24.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 5.0 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.