Decommissioned Fiberglass Wind Blade Cement Co-Feed
Product family: Zero-Landfill Composite Grind.
Flow: Repowered Wind Farms → Diamond Wire Section Port Cut → Primary Shredder & Metal Sep → Hammer Mill Controlled Fiber → Calorific Value & Ash Assay → Bulk Silo Truck to Cement → Cement Kiln & Panel Makers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Diamond Wire Section Port Cut | 1,530 s | 12 min | 95% | 98.1% | 6 | 19 (1.58 d) | 16 |
| 2. Primary Shredder & Metal Sep | 1,800 s | 15 min | 92% | 96.4% | 5 | 22 (1.83 d) | 12 |
| 3. Hammer Mill Controlled Fiber | 2,430 s | 20 min | 84% | 92.5% | 6 | 29 (2.42 d) | 8 |
| 4. Calorific Value & Ash Assay | 1,665 s | 8 min | 95% | 98.2% | 3 | 11 (0.92 d) | 14 |
| 5. Bulk Silo Truck to Cement | 1,260 s | 8 min | 97% | 99.4% | 3 | 10 (0.83 d) | 19 |
Key figures
- Takt time
- 2,250 s
- Lead time
- 9.32 d
- Value-added time
- 8,685 s
- Process cycle efficiency (PCE)
- 3.5%
- Rolled throughput yield (RTY)
- 85.4%
- Customer demand per day
- 12 tonnes
- Line capacity per day
- 8 tonnes
- Bottleneck
- Hammer Mill Controlled Fiber
Reading the bottleneck
The bottleneck is "Hammer Mill Controlled Fiber": it can process 8 tonnes per day against a demand of 12 tonnes, so it falls short of demand by 34.5%. Once downtime and scrap are counted, its cycle time grows from 2,430 s to 3,127 s, against a takt of 2,250 s. The largest loss at this step is equipment downtime (uptime 84%), about 463 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Reverse Logistics & Circular Refurbishment: Reverse Logistics & Circular Refurbishment
- Grade-A Smartphone Diagnostics & Battery Refurb
- Reusable Foldable Fresh Crate Wash & Loop
- Pooling & EPAL Wooden Pallet Inspection & Repair
- End-of-Life EV Battery Pack Second-Life SOH
- Corporate 3-Year Lease Laptop Refurbish Factory
- Regional Brewery Returnable Bottle Sort & Wash
- Laser Printer Toner Cartridge Remanufacturing
- Circular Second-Hand Apparel Steam, Photo & List
- Small Domestic Coffee & Vacuum Warranty Hub
- Hydrometallurgical Gold & Copper E-Waste Shred
- Pan-European Automotive Core Return & Credit Hub