Hypoallergenic Mild Surfactant Baby Pump Bottle
Product family: 500mL Tear-Free Wash Line.
Flow: Surfactant & HDPE Suppliers → Gentle Low-Shear Stir Mixing → Dermatology pH & Micro Release → Inline Piston Fill & Pump Fit → Torque Verify & Sleeve Label → Tray Erect & Shrink Bundle → Pharmacy & Grocery Channels
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Gentle Low-Shear Stir Mixing | 1.4 s | 60 min | 93% | 98.8% | 42,000 | 47,600 (1.70 d) | 33,866 |
| 2. Dermatology pH & Micro Release | 1.5 s | 15 min | 92% | 98.2% | 42,000 | 61,600 (2.20 d) | 32,162 |
| 3. Inline Piston Fill & Pump Fit | 2.1 s | 55 min | 84% | 96.4% | 28,000 | 50,400 (1.80 d) | 19,550 |
| 4. Torque Verify & Sleeve Label | 1.5 s | 20 min | 93% | 98.4% | 14,000 | 28,000 (1.00 d) | 31,480 |
| 5. Tray Erect & Shrink Bundle | 1.2 s | 10 min | 97% | 99.4% | 11,200 | 22,400 (0.80 d) | 42,183 |
Key figures
- Takt time
- 1.9 s
- Lead time
- 9.50 d
- Value-added time
- 7.7 s
- Process cycle efficiency (PCE)
- 0.002%
- Rolled throughput yield (RTY)
- 91.5%
- Customer demand per day
- 28,000 packs
- Line capacity per day
- 19,550 packs
- Bottleneck
- Inline Piston Fill & Pump Fit
Reading the bottleneck
The bottleneck is "Inline Piston Fill & Pump Fit": it can process 19,550 packs per day against a demand of 28,000 packs, so it falls short of demand by 30.2%. Once downtime and scrap are counted, its cycle time grows from 2.1 s to 2.6 s, against a takt of 1.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.4 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Cosmetics, Dermocare & Fragrances: Cosmetics, Dermocare & Fragrances
- Airless Pipette Hyaluronic Anti-Aging Serum
- Water-Resistant Mineral SPF50+ Tube Line
- Sulfate-Free Botanical Shampoo 400mL rPET
- Luxury EDP Eau de Parfum Alcohol Maceration
- Talc-Free Mineral Pressed Powder Compact Line
- Fluoride Whitening Laminated Tube Fill Line
- Butane-Propelled 150mL Aluminum Aerosol Line
- Biodegradable Viscose Baby & Micellar Wipe Line
- Silicone-Free Satin Lipstick Bullet Molding
- Ammonia-Free Cream Hair Color & Developer Kit
- Hydrogel Bio-Cellulose Facial Sheet Mask Line