Biodegradable Viscose Baby & Micellar Wipe Line

Product family: 64-Count Flip-Top Flowpacks.

Flow: Spunlace Non-Woven Supplier → Multi-Web Slit & Z-Fold Stack → Preservative Lotion Dose Wet → Horizontal Flowpack & Die-Cut → Hot-Melt Ultrasonic Rigid Lid → Case Packer & Palletize → Retail & Pharmacy Chains

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Biodegradable Viscose Baby & Micellar Wipe LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Spunlace Non-Woven Supplier → Multi-Web Slit & Z-Fold Stack (1.4 s) → Preservative Lotion Dose Wet (1.5 s) → Horizontal Flowpack & Die-Cut (2.1 s) → Hot-Melt Ultrasonic Rigid Lid (1.5 s) → Case Packer & Palletize (1.2 s) → Retail & Pharmacy Chains.SUPPLIERSpunlaceNon-WovenSupplierI1.70 d1Multi-Web Slit &Z-Fold StackC/T 1.4 sI2.20 d2PreservativeLotion Dose WetC/T 1.5 sI1.80 d3HorizontalFlowpack &…C/T 2.1 sI1.00 d4Hot-MeltUltrasonic Rigid…C/T 1.5 sI0.80 d5Case Packer &PalletizeC/T 1.2 sI2.00 dCUSTOMERRetail &Pharmacy Chains42,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Multi-Web Slit & Z-Fold Stack1.4 s60 min93%98.8%63,00071,400 (1.70 d)51,586
2. Preservative Lotion Dose Wet1.5 s15 min92%98.2%63,00092,400 (2.20 d)48,424
3. Horizontal Flowpack & Die-Cut2.1 s55 min84%96.4%42,00075,600 (1.80 d)29,961
4. Hot-Melt Ultrasonic Rigid Lid1.5 s20 min93%98.4%21,00042,000 (1.00 d)47,952
5. Case Packer & Palletize1.2 s10 min97%99.4%16,80033,600 (0.80 d)63,877

Key figures

Takt time
1.9 s
Lead time
9.50 d
Value-added time
7.7 s
Process cycle efficiency (PCE)
0.001%
Rolled throughput yield (RTY)
91.5%
Customer demand per day
42,000 packs
Line capacity per day
29,961 packs
Bottleneck
Horizontal Flowpack & Die-Cut

Reading the bottleneck

The bottleneck is "Horizontal Flowpack & Die-Cut": it can process 29,961 packs per day against a demand of 42,000 packs, so it falls short of demand by 28.7%. Once downtime and scrap are counted, its cycle time grows from 2.1 s to 2.6 s, against a takt of 1.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.