Butane-Propelled 150mL Aluminum Aerosol Line

Product family: ATEX High-Speed Deodorant Cans.

Flow: Aluminum Monobloc Can Supplier → Slurry Mix & Valve Insert → Under-Cup Gas Pressurize Fill → 50°C Hot-Water Tank Leak Check → Actuator Spray Head Snap → Checkweigh & Tray Wrap → European Mass Retail

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Butane-Propelled 150mL Aluminum Aerosol LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Aluminum Monobloc Can Supplier → Slurry Mix & Valve Insert (1.2 s) → Under-Cup Gas Pressurize Fill (1.2 s) → 50°C Hot-Water Tank Leak Check (1.7 s) → Actuator Spray Head Snap (1.2 s) → Checkweigh & Tray Wrap (1.2 s) → European Mass Retail.SUPPLIERAluminumMonobloc CanSupplierI1.70 d1Slurry Mix &Valve InsertC/T 1.2 sI2.20 d2Under-Cup GasPressurize FillC/T 1.2 sI1.80 d350°C Hot-WaterTank Leak CheckC/T 1.7 sI1.00 d4Actuator SprayHead SnapC/T 1.2 sI0.80 d5Checkweigh & TrayWrapC/T 1.2 sI2.00 dCUSTOMEREuropean MassRetail52,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Slurry Mix & Valve Insert1.2 s60 min93%98.8%78,00088,400 (1.70 d)60,184
2. Under-Cup Gas Pressurize Fill1.2 s15 min92%98.2%78,000114,400 (2.20 d)60,530
3. 50°C Hot-Water Tank Leak Check1.7 s55 min84%96.4%52,00093,600 (1.80 d)37,011
4. Actuator Spray Head Snap1.2 s20 min93%98.4%26,00052,000 (1.00 d)59,940
5. Checkweigh & Tray Wrap1.2 s10 min97%99.4%20,80041,600 (0.80 d)63,877

Key figures

Takt time
1.6 s
Lead time
9.50 d
Value-added time
6.5 s
Process cycle efficiency (PCE)
0.001%
Rolled throughput yield (RTY)
91.5%
Customer demand per day
52,000 packs
Line capacity per day
37,011 packs
Bottleneck
50°C Hot-Water Tank Leak Check

Reading the bottleneck

The bottleneck is "50°C Hot-Water Tank Leak Check": it can process 37,011 packs per day against a demand of 52,000 packs, so it falls short of demand by 28.8%. Once downtime and scrap are counted, its cycle time grows from 1.7 s to 2.1 s, against a takt of 1.6 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.