Water-Resistant Mineral SPF50+ Tube Line

Product family: Bio-Resin Sunscreen Tubes.

Flow: Zinc Oxide & Tube Suppliers → Dispersion Mill Non-Nano ZnO → Micro-Stability Centrifuge QC → Hot-Air PE Tube Weld & Fill → Batch Emboss & Checkweigh → Tray Pack & Pallet Stretch → Pharmacy & Mass Beauty

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Water-Resistant Mineral SPF50+ Tube LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Zinc Oxide & Tube Suppliers → Dispersion Mill Non-Nano ZnO (1.6 s) → Micro-Stability Centrifuge QC (1.8 s) → Hot-Air PE Tube Weld & Fill (2.4 s) → Batch Emboss & Checkweigh (1.7 s) → Tray Pack & Pallet Stretch (1.3 s) → Pharmacy & Mass Beauty.SUPPLIERZinc Oxide &Tube SuppliersI1.70 d1Dispersion MillNon-Nano ZnOC/T 1.6 sI2.20 d2Micro-StabilityCentrifuge QCC/T 1.8 sI1.80 d3Hot-Air PE TubeWeld & FillC/T 2.4 sI1.00 d4Batch Emboss &CheckweighC/T 1.7 sI0.80 d5Tray Pack &Pallet StretchC/T 1.3 sI2.00 dCUSTOMERPharmacy & MassBeauty24,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Dispersion Mill Non-Nano ZnO1.6 s60 min93%98.8%36,00040,800 (1.70 d)29,633
2. Micro-Stability Centrifuge QC1.8 s15 min92%98.2%36,00052,800 (2.20 d)26,802
3. Hot-Air PE Tube Weld & Fill2.4 s55 min84%96.4%24,00043,200 (1.80 d)17,106
4. Batch Emboss & Checkweigh1.7 s20 min93%98.4%12,00024,000 (1.00 d)27,777
5. Tray Pack & Pallet Stretch1.3 s10 min97%99.4%9,60019,200 (0.80 d)38,938

Key figures

Takt time
2.3 s
Lead time
9.50 d
Value-added time
8.8 s
Process cycle efficiency (PCE)
0.002%
Rolled throughput yield (RTY)
91.5%
Customer demand per day
24,000 packs
Line capacity per day
17,106 packs
Bottleneck
Hot-Air PE Tube Weld & Fill

Reading the bottleneck

The bottleneck is "Hot-Air PE Tube Weld & Fill": it can process 17,106 packs per day against a demand of 24,000 packs, so it falls short of demand by 28.7%. Once downtime and scrap are counted, its cycle time grows from 2.4 s to 3.0 s, against a takt of 2.3 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.5 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Cosmetics, Dermocare & Fragrances: Cosmetics, Dermocare & Fragrances