Silicone-Free Satin Lipstick Bullet Molding
Product family: Automated 12-Nozzle Lipstick Line.
Flow: Wax, Castor & Lake Pigments → Three-Roll Pigment Dispersion → 78°C Heated Nozzle Silic-Mold → Cold Tunnel Chill & Air Eject → Swivel Cup Insert & Flaming → Vision Tip Defect & Box → Prestige Beauty Houses
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Three-Roll Pigment Dispersion | 2.4 s | 60 min | 93% | 98.8% | 24,000 | 27,200 (1.70 d) | 19,755 |
| 2. 78°C Heated Nozzle Silic-Mold | 2.7 s | 15 min | 92% | 98.2% | 24,000 | 35,200 (2.20 d) | 17,868 |
| 3. Cold Tunnel Chill & Air Eject | 3.6 s | 55 min | 84% | 96.4% | 16,000 | 28,800 (1.80 d) | 11,404 |
| 4. Swivel Cup Insert & Flaming | 2.6 s | 20 min | 93% | 98.4% | 8,000 | 16,000 (1.00 d) | 18,162 |
| 5. Vision Tip Defect & Box | 1.9 s | 10 min | 97% | 99.4% | 6,400 | 12,800 (0.80 d) | 26,642 |
Key figures
- Takt time
- 3.4 s
- Lead time
- 9.50 d
- Value-added time
- 13.2 s
- Process cycle efficiency (PCE)
- 0.003%
- Rolled throughput yield (RTY)
- 91.5%
- Customer demand per day
- 16,000 units
- Line capacity per day
- 11,404 units
- Bottleneck
- Cold Tunnel Chill & Air Eject
Reading the bottleneck
The bottleneck is "Cold Tunnel Chill & Air Eject": it can process 11,404 units per day against a demand of 16,000 units, so it falls short of demand by 28.7%. Once downtime and scrap are counted, its cycle time grows from 3.6 s to 4.4 s, against a takt of 3.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Cosmetics, Dermocare & Fragrances: Cosmetics, Dermocare & Fragrances
- Airless Pipette Hyaluronic Anti-Aging Serum
- Water-Resistant Mineral SPF50+ Tube Line
- Sulfate-Free Botanical Shampoo 400mL rPET
- Luxury EDP Eau de Parfum Alcohol Maceration
- Talc-Free Mineral Pressed Powder Compact Line
- Fluoride Whitening Laminated Tube Fill Line
- Butane-Propelled 150mL Aluminum Aerosol Line
- Biodegradable Viscose Baby & Micellar Wipe Line
- Ammonia-Free Cream Hair Color & Developer Kit
- Hypoallergenic Mild Surfactant Baby Pump Bottle
- Hydrogel Bio-Cellulose Facial Sheet Mask Line